NCSX Independent Project Review Presentations

Tuesday, June 8

8:00 am DOE Federal Project Manager Perspective, G. Pitonak

9:00 am NCSX Project Status and Management Overview, H. Neilson

9:30 am Design Status: FDR Results WBS 12 (VV) and 14 (MCWF) summary, B. Nelson

10:15 am Plans for Procurement and Fabrication, P. Heitzenroeder

10:45 am Engineering Management Plans, Change Control, W. Reiersen

11:15 am Cost, Schedule, and Project Control Overview (incl. EVMS metrics), R Strykowsky

1:00 pm Modular Coil Windings (WBS 14), J. Chrzanowski

1:20 pm Conventional Coils and Structures (WBS 13/15), M. Kalish

1:35 pm Balance of Stellarator Core (WBS 16/17/18/19), B. Nelson

1:50 pm Test Cell Preparation/Machine Assembly (WBS 7), E. Perry

2:10 pm Power Systems (WBS4), S. Ramakrishnan

2:20 pm Ancillary Systems (WBS 2/3/5/6), L. Dudek

2:30 pm Startup & Operational Readiness Assessment (WBS85), C. Gentile

2:40 pm Management and Integration (WBS8), H. Neilson