NCSX Web Pages  

Project | Management | Physics | Procurement | Manufacturing

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > Design Review > WBS 131
Review Title TF Coil Wedge Casting FDR
Date 13 July 2005
Cognizant Engineer Mike Kalish
Responsible Line Manager Brad Nelson
Review Board Chairperson Hutch Neilson
Review Board Members Mike Cole, Jim Chrzanowski, Frank Malinowski, Steve Raftopoulos
Invitees Hutch Neilson, HM Fan, Fred Dahlgren, Geoff Gettelfinger, Mike Cole, Dave Williamson, Len Myatt, Kevin Freudenberg, Tom Brown
Attendees Frank Malinowski, Steve Raftopoulos, Brad Nelson, Mike Cole, Fred Dahlgren, Hutch Neilson, Bob Simmons, Jeff Makiel, Joe Rushinski, Horng-Ming Fan, Irving Zatz, Greg Pitonak, Brad Nelson, Mike Cole, Kevin Freudenberg, Dave Williamson, Tom Brown, Irving Zatz, Greg Pitonak
Charge 1. Are the wedge casting SOW and technical specification (C-spec) complete and ready to issue?

2. Is the drawing package complete and ready for fabrication?

3. Are the wedge casting and associated TF assembly analyses complete and checked? 

4. Is the design for integrating the wedge castings with the TF conductor sound and practical, including electrical insulation, bonding, fixturing?

5. Are the tolerances of the TF coil/ wedge casting assembly achievable and adequate for the final machine assembly?

Design Review Material

Announcement

Chits and Disposition Plan

Drawing

Presentation

C-Specification

Statement of Work

Design Review Report

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules  
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives    

Other review objectives addressed

(Attachment 4 of ENG-033)

 

Summary of Results

Disposition

(check  one)

 1  Acceptable
 1 Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
 1  Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1  Action required by Disposition is complete