Engineering > Design Review > WBS 18
Review Title Field Period Assembly Peer Review
Date 11 & 12 October 2006
Cognizant Engineer Mike Cole, Mike Viola, Tom Brown
Responsible Line Manager Larry Dudek, Brad Nelson
Review Board Chairperson Erik Perry
Review Board Members Jim Chrzanowski, Geoff Gettelfinger
Invitees Wayne Reiersen, Tom Brown, Fred Hurd, Gary Johnson, Jim Chrzanowski, Larry Dudek, Lutz Wegener, Mike Cole, Mike Viola, Tom McManamy, Torsten Braeuer, Erik Perry, Geoff Gettelfinger, Simon Anderson, Art Brooks, Bob Simmons, Brad Nelson, Brent Stratton, Fred Dahlgren, HM Fan, Hutch Neilson, Irv Zatz, Jeff Makiel, Jerry Levine, Joe Rushinski, Judy Malsbury, Kevin Freudenberg, Mike Williams, Mike Zarnstorff, Paul Fogarty, Paul Goranson, Phil Heitzenroeder, Ron Strykowsky, Steve Raftopoulos, Greg Pitonak; Jim Lyon, David Anderson, Steve Knowlton, Gary Johnson
Attendees Wayne Reiersen, Mike Viola, John Edwards, Art Brooks, Tom Brown, Phil Heitzenroeder, Geoff Gettelfinger, Jim Chrzanowski, Jeff Makiel, Judy Malsbury, Joe Rushinski, HM Fan, Bob Simmons, John Boscoe, Irving Zatz, Ron Strykowsky, Greg Pitonak, Steve Raftopoulos, Cynthia Phillips
Charge The purpose of the meeting is to assure that our approach to field period assembly is feasible, that the tooling design and metrology provisions are suitable, dimensional control requirements are realizable, and the schedule and resources appropriate. Erik Perry (PPPL) has agreed to chair the review. We have invited Lutz Wegener, Fred Hurd, and Torsten Braeuer from W7-X; David Anderson and Simon Anderson from HSX; Steve Knowlton from CTH; and Gary Johnson and Tom McManamy from SNS to participate in the review. In addition, we have asked Geoff Gettelfinger and Jim Chrzanowski to serve on the review committee.
Design Review Material

Announcement

Chits and Disposition

Presentation - Reiersen

Presentation - Brooks

Presentation - Cole

Presentation - Brown

Presentation - Viola

      -Movie Files-

MCHP - Shell 1

MCHP - Shell 2

MCHP - Shell 3

Local Back Tracking

Review Committee Report

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives  

Other review objectives addressed

(Attachment 4 of ENG-033)

   

Summary of Results

 

Disposition

(check  one)

 1 Acceptable
  1 Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
 1 Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete