List of Items for Future ECPs

 

Item Responsibility

 

Vacuum Vessel Spacer Piece Installation Fixture (WBS 17) - Gettlefinger

Gettlefinger
  WBS12/WBS 4 ICD CableRouting from Panel to Heaters Goranson
  WBS 1/WBS 4 Interfaces - need to Add Cost of Leads from Power Panels to Equipment WBS 13/14/15/16/17 Managers
  VVSA S/C - Marking of Stud Locations & Oversight & Support Viola/Strykowsky
  MC Winding Final Design Williamson/Strykowsky
  TRC Close-Out Costs Chrzanowski/Strykowsky
  MCWF Fracture Analysis Williamson/Strykowsky
  Metrology Support Program Raftopoulos/Strykowsky
  FP Assy Facility Prep Dsn & Install Brown/Strykowsky
     