WBS 11:  Paul Goranson WBS 12:  Paul Goranson Date of Agreement:   January 9, 2003
Project Engineer (s):  Brad Nelson (WBS 1) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies (1) Assess impact of incorporating a lithium divertor.

WBS 11 (Goranson)

Memo - Project will use as basis for establishing lithium-related performance and interface requirements. Needs to be done well in advance of when WBS 12 performance specification is due.  
  (2) Assess impact of incorporating a CFC liner with a divertor. 

WBS 11 (Goranson)

Memo - Project will use as basis for establishing envelope and interface requirements. Needs to be done well in advance of when WBS 12 performance specification is due.  
Functional Interfaces (1) Bakeout heat loads on the VV and In-Vessel Components.

WBS 11 (Goranson)

Maximum heat loads incorporated in WBS 11 and WBS 12 performance specifications. Needs to be done in advance of [1] when thermal analysis and cooling system is planned and [2] when WBS 12 performance (design-to) spec is due.  
Physical Interfaces (1) Physical interface between initial limiter and vacuum vessel.

WBS 11 (Goranson)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (2) Provisions required in vacuum vessel design to accommodate possible PFC upgrades.

WBS 11 (Goranson)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  

 

 


WBS 11:  Paul Goranson WBS 12:  Paul Goranson Date of Agreement:   January 9, 2003
Project Engineer (s):  Brad Nelson (WBS 1) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Physical Interfaces (3) Grounding connections between PFCs and vacuum vessel.

WBS 11 (Goranson)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (4) Provisions required in vacuum vessel design to accommodate internal trim coil upgrade.

WBS 11 (Goranson)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.