From: Raymond A. Camp Sent: Friday, July 22, 2005 4:06 PM To: Hutch Neilson Cc: Wayne T. Reiersen; jchrzano; Marianne Tyrrell Subject: ACC Review of CWF Stations Dear Dr. Neilson, The NCSX ACC reviewed the readiness of stations #1A, #1B and #4 of the CWF on Tuesday, July 20. Attending were J. Makeil (PG), L. Dietrich (PG), D. Mueller, R.Carnevale, J. Levine and myself. We were hosted by J. Chrzanowski, and W. Reiersen. Here are are recommendations: Station #1B - Casting prep including metrology, cleaning and poloidal-break meggar testing. Stud welding and cladding attachment by epoxy are also performed at this station. The ACC recommends that the operating procedure and JHA be signed off prior to operation of this station. Station #1A - Attaching the casting to the handling fixture ring and disassembly of the completed coil. The ACC recommends that the 1/2 Ton hoist be verified ready by M. Viola, the Labs lift engineer, prior to operation. Station #4 - This is the second coil winding station, with identical equipment to station #2. The ACC recommends that, prior to operation, the walkway from the back exit be delineated by tape or paint to assure door clearance and a clear emergency exit route. If you have any questions, please contact me. Thank you. Ray Camp NCSX ACC Chairperson