| Review
          Title | Field Period Assembly Plan 
        Peer Review | 
      
        | Date | 30 March 2004 | 
      
        | Cognizant
          Engineer | Mike Cole | 
      
        | Responsible Line Manager | Larry Dudek | 
      
        | Review Board Chairperson | Brad Nelson | 
      
        | Review Board Members | Erik Perry, Dave Williamson, 
        Mike Viola, Tom Brown | 
      
        | Invited Attendees | Frank Jones, Paul  
    Goranson, Kevin Freudenberg | 
      
        | Other Attendees |  | 
      
        | Charge | 1. Are the field period 
          assembly plans consistent with the design of the vacuum vessel and 
          modular coils? 2.  
          Are the procurement plans for the modular coil winding forms and 
          vacuum vessel segment assemblies consistent with the field period 
          assembly schedule? 3. Are the tooling 
          options adequate for field period assembly operations? 4. Are the planned 
          mockup adequate for training and practice purposes? | 
      
        | Design Review Material | 
        Announcement 
        
        Presentation   
        
        Chits and Project 
        Disposition 
        
        Critical Paths | 
      
        | Review Board Report |  | 
      
        | Items Reviewed | 
           | Sat | Unsat | Comments | 
      
        | Appropriate requirements identified |  |  |  | 
      
        | Development plans and schedules |  |  |  | 
      
        | Regulatory compliance including USQD and NEPA |  |  | N/A | 
      
        | Disposition of CHITS from previous reviews |  |  | Not Preserved | 
      
        | Cost 
          objectives |  |  |  | 
      
        | 
          Other 
          review objectives addressed 
          
          (Attachment 4 of ENG-033) |  |  |  | 
      
        | 
          Summary of Results | 1.Field period assembly plans 
    are consistent with the design of the vacuum vessel and modular coils. 
    2.Are the procurement plans for 
    the modular coil windings forms and vacuum vessel segment assemblies 
    consistent with the field period assembly schedule? 3.Are the tooling options 
    adequate for field period assembly operations? 4.Are the planned 
    mockups adequate for training and practice purposes?  
         | 
      
        | 
          Disposition 
          (check  
           one) | Acceptable | 
      
        | Acceptable pending resolution of concerns - 
    CHITS identified above must be resolved   prior to installation. | 
      
        | Incomplete -
    Additional design 
    work is required prior to another design review. | 
      
        | 
          Cog Engineer Close-out 
          (check  
           when done) |  | 
      
        | Action required by Disposition is complete |