Review Title Field Period Assembly Plan Peer Review
Date 30 March 2004
Cognizant Engineer Mike Cole
Responsible Line Manager Larry Dudek
Review Board Chairperson Brad Nelson
Review Board Members Erik Perry, Dave Williamson, Mike Viola, Tom Brown
Invited Attendees Frank Jones, Paul  Goranson, Kevin Freudenberg
Other Attendees  
Charge 1. Are the field period assembly plans consistent with the design of the vacuum vessel and modular coils?

2.  Are the procurement plans for the modular coil winding forms and vacuum vessel segment assemblies consistent with the field period assembly schedule?

3. Are the tooling options adequate for field period assembly operations?

4. Are the planned mockup adequate for training and practice purposes?

Design Review Material

Announcement

Presentation

Chits and Project Disposition

Critical Paths

Review Board Report  
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified      
Development plans and schedules    
Regulatory compliance including USQD and NEPA     N/A
Disposition of CHITS from previous reviews     Not Preserved
Cost objectives      

Other review objectives addressed

(Attachment 4 of ENG-033)

     

Summary of Results

1.Field period assembly plans are consistent with the design of the vacuum vessel and modular coils.

2.Are the procurement plans for the modular coil windings forms and vacuum vessel segment assemblies consistent with the field period assembly schedule?

3.Are the tooling options adequate for field period assembly operations?

4.Are the planned mockups adequate for training and practice purposes? 

Disposition

(check  one)

Acceptable
Acceptable pending resolution of concerns - CHITS identified above must be resolved   prior to installation.
Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 Action required by Disposition is complete
   