Review
Title |
D to C Site DC Transmission
System
(Out of Project Scope) |
Date |
14 May 2004 |
Cognizant
Engineer |
Henry Carnevale, Raki
Ramakrishnan |
Responsible
Line Manager |
Al von Halle |
Review Board Chairperson |
Al von Halle |
Review Board Members |
John Lacenere, Bob Parsells |
Invited Attendees |
Frank Malinowski, Art Wise,
Don McBride, Rick Van Kirk, Rich Borusovic, Larry Dudek, Jerry Levine |
Other Attendees |
Rod Templon, Ron Strykowsky,
Gary Oliaro, Leif Dietrich, K. Ranahan, Ed Lawson, Joe Byczkowski, Larry
Sutton, Mike Viola, Carl Potensky |
Charge |
|
Design Review Material |
Announcement
Presentation
Chits and Disposition |
Review Board Report |
|
Items Reviewed |
|
Sat |
Unsat |
Comments |
Appropriate requirements identified
|
|
|
|
Development plans and schedules |
|
|
ES&H and QC oversight to be
scheduled |
Regulatory compliance including USQD and NEPA |
|
|
|
Disposition of CHITS from previous reviews |
|
|
|
Cost
objectives |
|
|
|
Other
review objectives addressed
(Attachment 4 of ENG-033) |
|
|
|
Summary of Results
|
The charge of this committee was
to review the final design of the D to C Site Transmission System for the
NCSX project as designed by The Burns Group, Philadelphia, PA.
Available at this meeting were completed drawings of the structural support
system and cable trays to provide DC power to the NCSX Modular/TF/PF coil
systems from the D-Site supplies. Also available was the final version
of the Statement of Work for the installation of this system. This
review followed a CDR held in May of 2002, a PDR held in September of 2003,
and an intensive peer review of the preliminary drawings of this system in
February of 2004, during which 57 chits were generated. The thrust of
this FDR was to review the resolution of the concerns (chits) from the
review of the preliminary drawings in preparation for releasing g this
engineering package to Procurement. The proposed schedule calls
fro resolving all chits from this FDR, thereby finalizing this design by
5/19/04, initiating a procurement action by 5/21/04, and completing the
system installation by 9/15/04. The review committee agreed that
vendor responses to the procurement action are needed to finalize cost and
schedule estimates.
|
Disposition
(check
one) |
1
Acceptable |
Acceptable pending resolution of concerns -
CHITS identified above must be resolved prior to installation. |
1Incomplete -
Additional design
work is required prior to another design review.
|