NCSX Web Pages  

Project | Management | Physics | Procurement | Manufacturing

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > Design Review > WBS 142
Review Title C Type Upper and Lower Lead Blocks FDR
Date 03 June  2005
Cognizant Engineer Dave Williamson
Responsible Line Manager Brad Nelson
Review Board Chairperson Wayne Reiersen
Review Board Members Jim Chrzanowski, Larry Dudek, Phil Heitzenroeder, Art Brooks
Invitees Wayne Reiersen, Mike Zarnstorff, Paul Fogarty, Kevin Freudenberg, Steve Raftopoulos, Brent Stratton, Greg Pitonak, Jeff Makiel, Jim Chrzanowski, Larry Dudek, Phil Heitzenroeder, Art Brooks, Hutch Neilson
Attendees Brad Nelson, David Williamson, Jim Chrzanowski, Larry Dudek, Hutch Neilson, Art Brooks, Jeff Makiel, Wayne Reiersen, Bob Simmons, Paul Fogarty
Charge 1.     Does the lead block design

1.1   Provide a geometry into which the conductor can be readily “wound”?

1.2   Fix the conductors in the lead region in a repeatable pattern for each coil of the same type?

1.3   Support the conductor structurally?

1.4    Isolate the conductors from each other electrically?

1.5   Maintain cooling continuity in the lead region?

1.6   Stay within the geometric envelope used for VV/mod coil assembly?

1.7   Maintain acceptable field errors?

2.    Have the drawings and models been reviewed and are they ready for promotion to fabrication level?
Design Review Material

Announcement

Report

Presentation

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules  
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives    

Other review objectives addressed

(Attachment 4 of ENG-033)

   

Summary of Results

Disposition

(check  one)

 1  Acceptable
 1  Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
 1Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete