| Review
          Title | Coil Testing Control and 
		Protection Peer Review | 
      
        | Date | 09 June 2006 | 
      
        | Cognizant
          Engineer | Raki Ramakrishnan | 
      
        | Responsible Line Manager | Wayne Reiersen | 
      
        | Review Board Chairperson | Al von Halle | 
      
        | Review Board Members | Geoff Gettelfinger, Bob 
		Marsala, Wayne Reiersen, Mike Williams | 
      
        | Invitees | Bob Marsala, Raki 
		Ramakrishnan, Geoff Gettelfinger, Larry Dudek, Bob Woolley, Wayne 
		Reiersen, Don McBride, Gene Baker, Gregg Pitonak, Judy Malsbury, Colin 
		Phelps, Bob Simmons, Phil Heitzenroeder, Mike Williams, Jerry Levine, 
		Brad Nelson, Dave Williamson, Al vonHalle | 
      
        | Attendees | Larry Dudek, Bob Woolley, 
		Don McBride, Gene Baker, Judy Malsbury, Colin Phelps, Bob Simmons, Phil 
		Heitzenroeder, Gregg Pitonak, Brad Nelson, Dave Williamson, Kevin 
		Freudenberg | 
      
        | Charge | 
    	 | 
      
        | Design Review Material | 
        
        Announcement 
        
		Chits and Disposition 
		 
		 
        
		Presentation 
        
		Review Committee Report | 
      
        | Review Board Report |  | 
      
        | Items Reviewed | 
    
     | Sat | Unsat | Comments | 
      
        | Appropriate requirements identified |  |   |  | 
      
        | Development plans and schedules |  |   |  | 
      
        | Regulatory compliance including USQD and NEPA |  |   |  | 
      
        | Disposition of CHITS from previous reviews |  |   | N/A | 
      
        | Cost 
          objectives |  |    | Not covered in this review | 
      
        | 
          Other 
          review objectives addressed 
          
          (Attachment 4 of ENG-033) |  |   |  | 
      
        | 
          Summary of Results | 
		
		A peer review of the 
		additional control and protection systems needed to complete power 
		testing of the NCSX C1 coil with a known resistive line to ground 
		leakage path was held.  A design was received that would establish 
		an artificial null to minimize the potential at the known C1 coil 
		leakage path, and to provide ground fault protection via a ground fault 
		relay to be provided as shown in NCSX sketch B-4F1005. Voltage limiting 
		schemes were presented and discussed.  Metal Oxide Varistor (MOV), 
		added at both sides of the C1 coil, will clamp the coil voltage to 500 
		volts.  The test procedure will be updated to include warm/cold 
		coil Megger at 1 kV, and the daily ECS operating routines will include a 
		500 V Hipot of the entire circuit before rectifier power is applied.  
		Also, monitoring points will be brought out of the cryostat to provide 
		the ability to measure coil voltages at each terminal if required.  
		The review committee agreed that these systems should be implemented as 
		presented.    | 
      
        | 
          Disposition 
          (check 
     one) |  Acceptable | 
      
        | 1 Acceptable pending resolution of concerns - 
    CHITS identified above must be resolved prior to installation. | 
      
        | 1 Incomplete -
    Additional design 
    work is required prior to another design review. | 
      
        | 
          Cog Engineer Close-out 
          (check 
     when done) |  | 
      
        | 1  
    Action required by Disposition is complete |