NCSX Web Pages  

Project | Management | Physics | Procurement | Manufacturing

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > Design Review > WBS 182
Review Title Station 3 Tooling PDR
Date 30 October 2006
Cognizant Engineer  Tom Brown
Responsible Line Manager Larry Dudek
Review Board Chairperson Wayne Reiersen
Review Board Members Mike Viola, Phil Heitzenroeder, Art Brooks, Mike Cole
Invitees Wayne Reiersen, Tom Brown, Larry Dudek, Mike Viola, Mike Cole, HM Fan, Art Brooks, Phil Heitzenroeder, John Edwards, Steve Raftopoulos, Kevin Freudenberg, Paul Fogarty, Geoff Gettelfinger, Hutch Neilson, Mike Williams, Ron Strykowsky
Attendees Wayne Reiersen,
Charge 1. Make sure the requirements for the tooling is well defined (including dimensional control requirements)

2. Make sure we have a design which functionally meets those requirements (including a credible metrology approach)

3. Make sure that the tooling meets structural design criteria

4. Make sure that all chits from the Station 1 tooling have been addressed and relevant chits from the FPA Peer Review have been dispositioned and are being addressed

Design Review Material

Announcement

Chits and Disposition

Presentation - Brown

Review Committee Report

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives  

Other review objectives addressed

(Attachment 4 of ENG-033)

   

Summary of Results

 

Disposition

(check  one)

 1 Acceptable
  1 Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
 1 Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete

Privacy and Security Notice

Please forward comments and questions to the Webmaster