Review
Title |
Modular Coil Strain Gage
FDR |
Date |
24 January 2007 |
Cognizant
Engineer |
David
Williamson |
Responsible Line Manager |
Brad Nelson |
Review Board Chairperson |
Wayne Reiersen |
Review Board Members |
John Dong, Jim Chrzanowski,
Geoff Gettelfinger, Art Brooks, Tom Brown, Mike Cole |
Invitees |
Wayne Reiersen, Dave
Williamson, Kevin Freudenberg, Brad Nelson, Mike Cole, Mike Zarnstorff,
Larry Dudek, Tom Brown, Geoff Gettelfinger, Mike Williams, Phil
Heitzenroeder, Mike Viola, Jim Chrzanowski, John Dong, Art Brooks |
Attendees |
Jim Tsai, Dave Williamson, Kevin
Freudenberg, Mike Cole, Jim Chrzanowski, Tom Brown, John Dong, Geoff
Gettelfinger, Hutch Nelson, Wayne Reiersen, Paul Sichta, Phil Heitzenroeder
|
Charge |
|
Design Review Material |
Announcement
Chits and Disposition
Placement Presentation
Outline Presentation
Review Committee Report
|
Review Board Report |
|
Items Reviewed |
|
Sat |
Unsat |
Comments |
Appropriate requirements identified
|
|
|
|
Development plans and schedules |
|
|
|
Regulatory compliance including USQD and NEPA |
|
|
|
Disposition of CHITS from previous reviews |
|
|
|
Cost
objectives |
|
|
|
Other
review objectives addressed
(Attachment 4 of ENG-033) |
|
|
|
Summary of Results
|
|
Disposition
(check
one) |
1 Acceptable |
1 Acceptable pending resolution of concerns -
CHITS identified above must be resolved prior to installation. |
Incomplete -
Additional design
work is required prior to another design review.
|
Cog Engineer Close-out
(check
when done) |
|
1