Review Title Rogowski Coil CDR
Date 18 April  2007
Cognizant Engineer George Labik
Responsible Line Manager Brent Stratton
Review Board Chairperson Mike Zarnstorff
Review Board Members George Labik, Robert Kaita, Mike Zarnstorff, Stefan Gerhardt, Jim Chrzanowski,           Geoff  Gettelfinger
Invitees George Labik, Tom Brown, Jim Chrzanowski, Larry Dudek, Stefan Gerhardt, Geoff Gettelfinger, Bob Kaita, Wayne Reiersen, Brent Stratton, Mike Viola, Mike Zarnstorff, Mike Cole, Paul Goranson, Brad Nelson. 
Attendees Jim Chrzanowski, Stefan Gerhardt, Bob Kaita, Geoff Gettelfinger, Hutch Neilson, Mike Zarnstorff,  Paul (P.J.) Fogarty, Fred Dahlgren, Larry Guttadora
Charge 1. Define a suitable and workable design

2. Define a set of requirements

3. Obtain approval to proceed to a PDR

Design Review Material

Announcement

Chits and Disposition

Presentation

Review Committee Report

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives  

Other review objectives addressed

(Attachment 4 of ENG-033)

   

Summary of Results

 

Disposition

(check  one)

 1 Acceptable
  1 Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
  1 Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete