NCSX Web Pages  

Project | Management | Physics | Procurement | Manufacturing

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > Design Review > WBS 132
 
Review Title PF Coil PDR
Date 14 December 2007
Cognizant Engineer Mike Kalish
Responsible Line Manager Phil Heitzenroeder
Review Board Chairperson Charles Neumeyer
Review Board Members Phil Heitzenroeder, Charles Neumeyer, Mike Bird (NHMFL), Jim Chrzanowski, Larry Dudek
Invitees Jeff Makiel, Jerry Levine, Judy Malsbury, Jim Anderson, Don Rej, Hutch Neilson, Raki Ramakrishnan, Tom Brown, Fred Dahlgren, Mike Cole, W. Ted Hunter
Attendees Mike Cole, Chuck Swenson, Jim Chrzanowski, Raki Ramakrishnan, Charlie Neumeyer, Phil Heitzenroeder, Judy Malsbury, Bob Simmons, Tom Meighan, Steve Raftopoulos , Hutch Neilson, Ron Strykowsky, Jim Anderson, Frank Malinowski, Art Brooks, Larry Sutton, Joe Rushinski, Fred Dahlgren
Charge

The committee is to evaluate the degree of success of the review with regards to the following requirements as required by PPPL Engineering Procedure ENG-033, Rev. 2:

  • Verify that all requirements are being addressed. Identify requirement or design conflict and potential "show stoppers"
  • Review the result of analyses, calculations, and tests conducted to obtain additional information for the design
  • Review w the ability to implement the proposed design taking into consideration capabilities, tolerances, costs, quality reliability and ES& H security
  • Review test requirements and plans
  • Review updated design and development plans and schedules
  • Assure the appropriate incorporation of recommendations from previous design reviews
  • Review manufacturability
Design Review Material

Announcement

Chits and Disposition

Presentation

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified X   Need to document V&I requirements (chit #2)
Development plans and schedules X
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives    

Other review objectives addressed

(Attachment 4 of ENG-033)

   

Summary of Results

14 Chits submitted.  Most were associated with bolts, & bolt criteria, and checking.  A chit suggesting upgrading the bolts from grade 5 to grade 8 was accepted. The calculations allowable, and calculation checking will all be included in this change.

Disposition

(check  one)

 1 Acceptable
  Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
  1 Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete

Privacy and Security Notice

Please forward comments and questions to the Webmaster