Review
Title |
Trim Coils PDR |
Date |
24 March 2008 |
Cognizant
Engineer |
Mike Kalish |
Responsible Line Manager |
Phil Heitzenroeder |
Review Board Chairperson |
Al von Halle |
Review Board Members |
Raki Ramakrishnan, Jim
Chrzanowski, Fred Dahlgren, Ron Hatcher |
Invitees |
Don Rej, Hutch Neilson, Jeff
Harris, Jeff Makiel, Jerry Levine, Judy Malsbury, Mike Cole, Mike
Williams, Mike Zarnstorff, Wayne Reiersen, Al von Halle, Fred Dahlgren,
Mike Kalish, Bob Simmons |
Attendees |
Hutch Neilson, Tom Meighan,
Joe Rushinski, Kevin Ranahan, Brent Stratton, Phil Heitzenroeder, Art
Brooks, Jeff Makiel, Bob Simmons, Steve Raftopoulos, Jeff Harris, Ron
Hatcher, Fred Dahlgren, Jim Chrzanowski, Raki Ramakrishnan, Al vonHalle,
Mike Kalish |
Charge |
The charge
to the review committee is as follows:
1) Is the Systems Requirements Document
adequate and finalized? Are
interfaces defined?
2) Is the design consistent with the
requirements?
3) Are the design basis analyses and
any supporting R&D documented and
adequate?
4) Are the drawings and models at the
Preliminary Design level?
5) Have chits from the CDR been
addressed? |
Design Review Material |
Announcement
Chits and Disposition
Presentation
|
Review Board Report |
|
Items Reviewed |
|
Sat |
Unsat |
Comments |
Appropriate requirements identified
|
|
|
GRD/SRD Updates needed (see
chits) |
Development plans and schedules |
|
|
|
Regulatory compliance including USQD and NEPA |
|
|
Not Covered in this review |
Disposition of CHITS from previous reviews |
|
|
Peer review chits |
Cost
objectives |
|
|
Not covered in this review |
Other
review objectives addressed
(Attachment 4 of ENG-033) |
|
|
|
Summary of Results
|
The preliminary
design of the NCSX trim coils was reviewed. Preliminary drawings and a
draft of the System Requirements Document (SRD) were available, and the
optimization/evolution of the design vs. design objectives/margins was
presented. Material specifications (although not complete) and proposed
winding schemes were reviewed in the light of system requirements. The
coil mounting structure was reviewed, but material for clamps has not
yet been specified, and details for both the coil mounting and coil lead
structures need to be further developed. Preliminary stress analysis
for both the coil and mounting structures was presented, which has
resulted in the proposed stiffening of the coil corners, and will have
to be revisited in stress analysis of the final design configuration.
Coil cooling analysis was reviewed, as well as the resolutions of chits
from a previous peer review.
There were 18 chits
recorded during this review, concerning system requirements and
interfaces, required analysis, and proposed changes to design details.
The review committee concurred with all chits, and agreed that this
review was successful pending resolution of the chits. |
Disposition
(check
one) |
1 Acceptable |
Acceptable pending resolution of concerns -
CHITS identified above must be resolved prior to installation. |
1 Incomplete -
Additional design
work is required prior to another design review.
|
Cog Engineer Close-out
(check
when done) |
|
1
Action required by Disposition is complete |