NCSX Web Pages  

Project | Management | Physics | Procurement | Manufacturing

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > Design Review > WBS 15
 
Review Title NCSX Coil Structures FDR
Date 06 August 2008
Cognizant Engineer Fred Dahlgren
Responsible Line Manager Phil Heitzenroeder
Review Board Chairperson Larry Dudek
Review Board Members Phil Heitzenroeder, Hutch Neilson, Larry Dudek, Mike Kalish, Art Brooks, H.M. Fan
Invitees Tom Brown, Judy Malsbury, Jeff Makiel, Jerry Levine, Hutch Neilson, Don Rej, Mike Williams, Steve Raftopoulos, Jim Chrzanowski, Larry Dudek, Mike Kalish, Art Brooks, H. M. Fan, Phil Heitzenroeder
Attendees Tom Brown, Jeff Makiel, Jerry Levine, Hutch Neilson, Don Rej, Jim Chrzanowski, Bob Simmons, Sri Avasarala
Charge 1. Are all required analyses complete and formally checked and adequate to establish that the proposed design is feasible and meets established design criteria?

2. Are the drawings and documentation adequate to support the procurement and/ or manufacturing process, installation, and ready for sign-off?

3. Are the design of the coil structures compatible with machine assembly ?

4. Is the Product Specification (CSPEC) complete and satisfactory? Are the interfaces adequately defined?

5. Is the Work Planning form current, and have the applicable requirements been satisfied?

6. Have the chits from the PDR been resolved?

7. Are updated cost and schedule estimates available?

Design Review Material

Announcement

Chits and Disposition

Presentation
Animated Slide

Summary

Review Board Report  
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives    

Other review objectives addressed

(Attachment 4 of ENG-033)

 

Summary of Results

Please see link under Design Review Material

Disposition

(check  one)

 1  Acceptable
  1  Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
  1 Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete

Privacy and Security Notice

Please forward comments and questions to the Webmaster