Database: NCSX PUNCHLIST.fp7 |
Records: 593 |
Task No. | Item | Ref. | Description | Work Status | Update | Status |
T-274 | Coil A-1 | | Documentation package complete and ready for copy | In-Progress | | OPEN |
T-496 | Coil A-1 | | Install batt insulation | Complete | | QA CHECK |
T-280 | Coil B-1 | | Documentation package complete and ready for copy | In-Progress | | OPEN |
T-502 | Coil B-1 | | Install batt insulation | Not Started | | OPEN |
T-268 | Coil C-1 | | Documentation package complete and ready for copy | In-Progress | | OPEN |
T-508 | Coil C-1 | | Install batt insulation | Complete | | QA CHECK |
T-588 | Coil C-1 | | Electrical test (7.5 kV) following winding form re-work | Not Started | | OPEN |