Database: NCSX PUNCHLIST.fp7
Records: 593
Task No.ItemRef.DescriptionWork StatusUpdateStatus
T-203Coil A-2Install thermocouples (coil areas)In-ProgressOPEN
T-275Coil A-2Documentation package complete and ready for copyIn-ProgressOPEN
T-345Coil A-2Grind overcastingIn-ProgressSmall spot on B flange still neededOPEN
T-497Coil A-2Install batt insulationCompleteQA CHECK
T-577Coil A-2Electrical test (7.5 kV) following winding form re-workNot StartedOPEN
T-209Coil B-2Install thermocouples (coil areas)In-ProgressOPEN
T-281Coil B-2Documentation package complete and ready for copyIn-ProgressOPEN
T-351Coil B-2Grind overcastingIn-ProgressGrind additional areas noted in B1-C1 gross fitOPEN
T-503Coil B-2Install batt insulationCompleteQA CHECK
T-583Coil B-2Electrical test (7.5 kV) following winding form re-workNot StartedOPEN
T-197Coil C-2Install thermocouples (coil areas)In-ProgressOPEN
T-269Coil C-2Documentation package complete and ready for copyIn-ProgressOPEN
T-357Coil C-2Grind overcastingNot StartedGrind additional areas noted in B1-C1 gross fitOPEN
T-509Coil C-2Install batt insulationNot StartedOPEN
T-589Coil C-2Electrical test (7.5 kV) following winding form re-workNot StartedOPEN
T-517VVSA-1A2 to B2 gross fit testNot StartedOPEN
T-518VVSA-1B2 to C2 gross fit testNot StartedOPEN
FileMaker Pro Version: 8.0v3
Build: 03-20-2006