Database: NCSX PUNCHLIST.fp7 |
Records: 593 |
Task No. | Item | Description | FPA | Status | Date Closed |
T-309 | | NOT USED | | CLOSED | |
T-304 | | NOT USED | | CLOSED | |
T-303 | | NOT USED | | CLOSED | |
T-302 | | NOT USED | | CLOSED | |
T-301 | | NOT USED | | CLOSED | |
T-300 | | NOT USED | | CLOSED | |
T-299 | | NOT USED | | CLOSED | |
T-298 | | NOT USED | | CLOSED | |
T-297 | | NOT USED | | CLOSED | |
T-296 | | NOT USED | | CLOSED | |
T-295 | | NOT USED | | CLOSED | |
T-294 | | NOT USED | | CLOSED | |
T-293 | | NOT USED | | CLOSED | |
T-292 | | NOT USED | | CLOSED | |
T-291 | | NOT USED | | CLOSED | |
T-290 | | NOT USED | | CLOSED | |
T-289 | | NOT USED | | CLOSED | |
T-288 | | NOT USED | | CLOSED | |
T-287 | | NOT USED | | CLOSED | |
T-286 | | NOT USED | | CLOSED | |
T-036 | | NOT USED | No | CLOSED | |
T-035 | | NOT USED | No | CLOSED | |
T-034 | | NOT USED | No | CLOSED | |
T-033 | | NOT USED | No | CLOSED | |
T-032 | | NOT USED | No | CLOSED | |
T-031 | | NOT USED | No | CLOSED | |
T-030 | | NOT USED | No | CLOSED | |
T-029 | | NOT USED | No | CLOSED | |
T-028 | | NOT USED | No | CLOSED | |
T-027 | | NOT USED | No | CLOSED | |
T-026 | | NOT USED | No | CLOSED | |
T-025 | | NOT USED | No | CLOSED | |
T-024 | | NOT USED | No | CLOSED | |
T-023 | | NOT USED | No | CLOSED | |
T-022 | | NOT USED | No | CLOSED | |
T-021 | | NOT USED | No | CLOSED | |
T-020 | | NOT USED | No | CLOSED | |
T-019 | | NOT USED | No | CLOSED | |
T-018 | | NOT USED | Yes | CLOSED | |
T-017 | | NOT USED | Yes | CLOSED | |
T-016 | | NOT USED | Yes | CLOSED | |
T-015 | | NOT USED | Yes | CLOSED | |
T-014 | | NOT USED | Yes | CLOSED | |
T-013 | | NOT USED | Yes | CLOSED | |
T-012 | | NOT USED | Yes | CLOSED | |
T-011 | | NOT USED | Yes | CLOSED | |
T-010 | | NOT USED | No | CLOSED | |
T-009 | | NOT USED | Yes | CLOSED | |
T-008 | | NOT USED | Yes | CLOSED | |
T-576 | Coil A-1 | Electrical test (7.5 kV) following winding form re-work | Yes | CLOSED | 1/8/2008 |
T-551 | Coil A-1 | Remove epoxy overflow fittings | Yes | CLOSED | 9/6/2007 |
T-533 | Coil A-1 | Fabricate Bushings | Yes | CLOSED | 9/7/2007 |
T-496 | Coil A-1 | Install batt insulation | Yes | QA CHECK | |
T-464 | Coil A-1 | Correct clamp interference (#59, 61) | Yes | CLOSED | 9/6/2007 |
T-454 | Coil A-1 | Secure terminal lug hardware | No | CLOSED | 10/25/2007 |
T-416 | Coil A-1 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 5/22/2007 |
T-398 | Coil A-1 | Check thread engagement on tapped holes | Yes | CLOSED | 5/22/2007 |
T-380 | Coil A-1 | Grinding/milling to accommodate nut access | Yes | CLOSED | 8/24/2007 |
T-362 | Coil A-1 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-344 | Coil A-1 | Grind overcasting | Yes | CLOSED | 6/15/2007 |
T-326 | Coil A-1 | Metrology (pre-measurement) also scan coil to vessel boss connection | Yes | CLOSED | 10/5/2007 |
T-321 | Coil A-1 | Repair (2) threaded flange plugs | Yes | CLOSED | 8/24/2007 |
T-320 | Coil A-1 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-274 | Coil A-1 | Documentation package complete and ready for copy | Yes | OPEN | |
T-256 | Coil A-1 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 4/12/2007 |
T-238 | Coil A-1 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 4/12/2007 |
T-220 | Coil A-1 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-202 | Coil A-1 | Install thermocouples (coil areas) | Yes | CLOSED | 1/10/2008 |
T-184 | Coil A-1 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-166 | Coil A-1 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-155 | Coil A-1 | Grind wing area type A coils | Yes | CLOSED | 5/29/2007 |
T-143 | Coil A-1 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 10/18/2007 |
T-125 | Coil A-1 | Cover entire lead area with cover/box | No | OPEN | |
T-107 | Coil A-1 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 10/22/2007 |
T-073 | Coil A-1 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-039 | Coil A-1 | Cut fingers of top chill plates | Yes | CLOSED | 4/2/2007 |
T-577 | Coil A-2 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-574 | Coil A-2 | Repair damaged cooling tubes | Yes | CLOSED | 10/22/2007 |
T-552 | Coil A-2 | Remove epoxy overflow fittings | Yes | CLOSED | 10/3/2007 |
T-534 | Coil A-2 | Fabricate Bushings | Yes | CLOSED | 9/27/2007 |
T-497 | Coil A-2 | Install batt insulation | Yes | QA CHECK | |
T-486 | Coil A-2 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-465 | Coil A-2 | Correct clamp interference (#59, 61) | Yes | CLOSED | 10/22/2007 |
T-455 | Coil A-2 | Secure terminal lug hardware | No | CLOSED | 10/24/2007 |
T-417 | Coil A-2 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 6/26/2007 |
T-399 | Coil A-2 | Check thread engagement on tapped holes | Yes | CLOSED | 6/26/2007 |
T-381 | Coil A-2 | Grinding/milling to accommodate nut access | Yes | CLOSED | 7/20/2007 |
T-363 | Coil A-2 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-345 | Coil A-2 | Grind overcasting | Yes | OPEN | |
T-327 | Coil A-2 | Metrology (pre-measurement) also scan coil to vessel boss connection | Yes | CLOSED | 10/16/2007 |
T-275 | Coil A-2 | Documentation package complete and ready for copy | Yes | OPEN | |
T-257 | Coil A-2 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 6/15/2007 |
T-239 | Coil A-2 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 6/15/2007 |
T-221 | Coil A-2 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-203 | Coil A-2 | Install thermocouples (coil areas) | Yes | OPEN | |
T-185 | Coil A-2 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-167 | Coil A-2 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-156 | Coil A-2 | Grind wing area type A coils | Yes | CLOSED | 6/15/2007 |
T-144 | Coil A-2 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 10/22/2007 |
T-126 | Coil A-2 | Cover entire lead area with cover/box | No | OPEN | |
T-108 | Coil A-2 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 6/15/2007 |
T-074 | Coil A-2 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-040 | Coil A-2 | Cut fingers of top chill plates | Yes | CLOSED | 6/15/2007 |
T-578 | Coil A-3 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-553 | Coil A-3 | Remove epoxy overflow fittings | Yes | CLOSED | 12/7/2007 |
T-535 | Coil A-3 | Fabricate Bushings | Yes | CLOSED | 10/12/2007 |
T-498 | Coil A-3 | Install batt insulation | Yes | QA CHECK | |
T-487 | Coil A-3 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-466 | Coil A-3 | Correct clamp interference (#59, 61) | Yes | CLOSED | 8/20/2007 |
T-456 | Coil A-3 | Secure terminal lug hardware | No | CLOSED | 12/7/2007 |
T-437 | Coil A-3 | Add more fiducials | Yes | CLOSED | 11/13/2007 |
T-418 | Coil A-3 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 4/20/2007 |
T-400 | Coil A-3 | Check thread engagement on tapped holes | Yes | CLOSED | 4/20/2007 |
T-382 | Coil A-3 | Grinding/milling to accommodate nut access | Yes | CLOSED | 9/6/2007 |
T-364 | Coil A-3 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-346 | Coil A-3 | Grind overcasting | Yes | CLOSED | 9/6/2007 |
T-328 | Coil A-3 | Metrology (pre-measurement) also scan coil to vessel boss connection | Yes | CLOSED | 12/5/2007 |
T-276 | Coil A-3 | Documentation package complete and ready for copy | Yes | OPEN | |
T-258 | Coil A-3 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 8/15/2007 |
T-240 | Coil A-3 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 4/12/2007 |
T-222 | Coil A-3 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-204 | Coil A-3 | Install thermocouples (coil areas) | Yes | OPEN | |
T-186 | Coil A-3 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-168 | Coil A-3 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-145 | Coil A-3 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 12/7/2007 |
T-127 | Coil A-3 | Cover entire lead area with cover/box | No | OPEN | |
T-109 | Coil A-3 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 12/7/2007 |
T-075 | Coil A-3 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-041 | Coil A-3 | Cut fingers of top chill plates | Yes | CLOSED | 4/2/2007 |
T-579 | Coil A-4 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-565 | Coil A-4 | Secure terminal lug hardware | No | CLOSED | 12/18/2007 |
T-554 | Coil A-4 | Remove epoxy overflow fittings | Yes | CLOSED | 9/7/2007 |
T-536 | Coil A-4 | Fabricate Bushings | Yes | OPEN | |
T-531 | Coil A-4 | Repair dented cooling tube/Retest | Yes | OPEN | |
T-499 | Coil A-4 | Install batt insulation | Yes | OPEN | |
T-488 | Coil A-4 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-467 | Coil A-4 | Correct clamp interference (#59, 61) | Yes | OPEN | |
T-438 | Coil A-4 | Add more fiducials | Yes | CLOSED | 12/19/2007 |
T-419 | Coil A-4 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 7/17/2007 |
T-401 | Coil A-4 | Check thread engagement on tapped holes | Yes | CLOSED | 7/17/2007 |
T-383 | Coil A-4 | Grinding/milling to accommodate nut access | Yes | CLOSED | 9/7/2007 |
T-365 | Coil A-4 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-347 | Coil A-4 | Grind overcasting | Yes | CLOSED | 9/7/2007 |
T-329 | Coil A-4 | Metrology (pre-measurement) also scan coil to vessel boss connection | Yes | OPEN | |
T-277 | Coil A-4 | Documentation package complete and ready for copy | Yes | OPEN | |
T-259 | Coil A-4 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 7/17/2007 |
T-241 | Coil A-4 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 7/17/2007 |
T-223 | Coil A-4 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-205 | Coil A-4 | Install thermocouples (coil areas) | Yes | OPEN | |
T-187 | Coil A-4 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-169 | Coil A-4 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-157 | Coil A-4 | Grind wing area type A coils | Yes | CLOSED | 9/7/2007 |
T-146 | Coil A-4 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 12/18/2007 |
T-128 | Coil A-4 | Cover entire lead area with cover/box | No | OPEN | |
T-110 | Coil A-4 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 7/17/2007 |
T-094 | Coil A-4 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | CLOSED | 7/17/2007 |
T-086 | Coil A-4 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | CLOSED | 7/17/2007 |
T-076 | Coil A-4 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-060 | Coil A-4 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | CLOSED | 7/17/2007 |
T-052 | Coil A-4 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | CLOSED | 4/2/2007 |
T-042 | Coil A-4 | Cut fingers of top chill plates | Yes | CLOSED | 7/17/2007 |
T-580 | Coil A-5 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-566 | Coil A-5 | Secure terminal lug hardware | No | OPEN | |
T-555 | Coil A-5 | Remove epoxy overflow fittings | Yes | OPEN | |
T-537 | Coil A-5 | Fabricate Bushings | Yes | CLOSED | 12/5/2007 |
T-500 | Coil A-5 | Install batt insulation | Yes | QA CHECK | |
T-489 | Coil A-5 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-468 | Coil A-5 | Correct clamp interference (#59, 61) | Yes | CLOSED | 11/12/2007 |
T-439 | Coil A-5 | Add more fiducials | Yes | CLOSED | 12/4/2007 |
T-435 | Coil A-5 | Remove supplier's tooling ball inserts | Yes | OPEN | |
T-420 | Coil A-5 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-402 | Coil A-5 | Check thread engagement on tapped holes | Yes | OPEN | |
T-384 | Coil A-5 | Grinding/milling to accommodate nut access | Yes | OPEN | |
T-366 | Coil A-5 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-348 | Coil A-5 | Grind overcasting | Yes | OPEN | |
T-330 | Coil A-5 | Metrology (pre-measurement) also scan coil to vessel boss connection | Yes | CLOSED | 12/18/2007 |
T-278 | Coil A-5 | Documentation package complete and ready for copy | Yes | OPEN | |
T-260 | Coil A-5 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 12/7/2007 |
T-242 | Coil A-5 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 11/12/2007 |
T-224 | Coil A-5 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/12/2007 |
T-206 | Coil A-5 | Install thermocouples (coil areas) | Yes | OPEN | |
T-188 | Coil A-5 | Install strain gauges- fiber optic | Yes | OPEN | |
T-170 | Coil A-5 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-158 | Coil A-5 | Grind wing area type A coils | Yes | OPEN | |
T-147 | Coil A-5 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 12/17/2007 |
T-129 | Coil A-5 | Cover entire lead area with cover/box | No | OPEN | |
T-111 | Coil A-5 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 11/12/2007 |
T-095 | Coil A-5 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | CLOSED | 12/7/2007 |
T-087 | Coil A-5 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | CLOSED | 11/12/2007 |
T-077 | Coil A-5 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-061 | Coil A-5 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | OPEN | |
T-053 | Coil A-5 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | CLOSED | 11/12/2007 |
T-043 | Coil A-5 | Cut fingers of top chill plates | Yes | CLOSED | 11/12/2007 |
T-581 | Coil A-6 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-556 | Coil A-6 | Remove epoxy overflow fittings | Yes | OPEN | |
T-538 | Coil A-6 | Fabricate Bushings | Yes | OPEN | |
T-501 | Coil A-6 | Install batt insulation | Yes | OPEN | |
T-490 | Coil A-6 | Complete electrical tests following VPI | Yes | OPEN | |
T-469 | Coil A-6 | Correct clamp interference (#59, 61) | Yes | OPEN | |
T-440 | Coil A-6 | Add more fiducials | Yes | CLOSED | 7/17/2007 |
T-436 | Coil A-6 | Remove supplier's tooling ball inserts | Yes | OPEN | |
T-421 | Coil A-6 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-403 | Coil A-6 | Check thread engagement on tapped holes | Yes | OPEN | |
T-385 | Coil A-6 | Grinding/milling to accommodate nut access | Yes | CLOSED | 10/5/2007 |
T-367 | Coil A-6 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-349 | Coil A-6 | Grind overcasting | Yes | CLOSED | 12/17/2007 |
T-331 | Coil A-6 | Metrology (pre-measurement) also scan coil to vessel boss connection | Yes | OPEN | |
T-279 | Coil A-6 | Documentation package complete and ready for copy | Yes | OPEN | |
T-261 | Coil A-6 | Mount final co-wound diagnostic box to casting | Yes | OPEN | |
T-243 | Coil A-6 | Lock all clamp hardware- weld locking wire | Yes | OPEN | |
T-225 | Coil A-6 | Modify final coil clamps- permeability & fitup issues | Yes | OPEN | |
T-207 | Coil A-6 | Install thermocouples (coil areas) | Yes | OPEN | |
T-189 | Coil A-6 | Install strain gauges- fiber optic | Yes | OPEN | |
T-171 | Coil A-6 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-159 | Coil A-6 | Grind wing area type A coils | Yes | CLOSED | 10/5/2007 |
T-148 | Coil A-6 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 11/8/2007 |
T-130 | Coil A-6 | Cover entire lead area with cover/box | No | OPEN | |
T-112 | Coil A-6 | Electrically tie the three jumper studs to the bottom jumper | No | OPEN | |
T-096 | Coil A-6 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | OPEN | |
T-088 | Coil A-6 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | OPEN | |
T-078 | Coil A-6 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-062 | Coil A-6 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | OPEN | |
T-054 | Coil A-6 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | OPEN | |
T-044 | Coil A-6 | Cut fingers of top chill plates | Yes | OPEN | |
T-582 | Coil B-1 | Electrical test (7.5 kV) following winding form re-work | Yes | CLOSED | 1/8/2008 |
T-567 | Coil B-1 | Secure terminal lug hardware | No | CLOSED | 11/8/2007 |
T-557 | Coil B-1 | Remove epoxy overflow fittings | Yes | CLOSED | 9/17/2007 |
T-539 | Coil B-1 | Fabricate Bushings | Yes | CLOSED | 9/5/2007 |
T-502 | Coil B-1 | Install batt insulation | Yes | OPEN | |
T-470 | Coil B-1 | Correct clamp interference (#60, 69) | Yes | CLOSED | 8/21/2007 |
T-463 | Coil B-1 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-441 | Coil B-1 | Add more fiducials | Yes | CLOSED | 5/7/2007 |
T-422 | Coil B-1 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 5/24/2007 |
T-404 | Coil B-1 | Check thread engagement on tapped holes | Yes | CLOSED | 5/24/2007 |
T-386 | Coil B-1 | Grinding/milling to accommodate nut access | Yes | CLOSED | 7/26/2007 |
T-368 | Coil B-1 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-350 | Coil B-1 | Grind overcasting | Yes | CLOSED | 1/11/2008 |
T-332 | Coil B-1 | Metrology (pre-measurement) | Yes | CLOSED | 8/7/2007 |
T-280 | Coil B-1 | Documentation package complete and ready for copy | Yes | OPEN | |
T-262 | Coil B-1 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 5/16/2007 |
T-244 | Coil B-1 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 5/16/2007 |
T-226 | Coil B-1 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-208 | Coil B-1 | Install thermocouples (coil areas) | Yes | CLOSED | 1/10/2008 |
T-190 | Coil B-1 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-172 | Coil B-1 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-149 | Coil B-1 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 11/8/2007 |
T-131 | Coil B-1 | Cover entire lead area with cover/box | No | OPEN | |
T-113 | Coil B-1 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 5/16/2007 |
T-079 | Coil B-1 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-045 | Coil B-1 | Cut fingers of top chill plates | Yes | CLOSED | 4/2/2007 |
T-583 | Coil B-2 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-568 | Coil B-2 | Secure terminal lug hardware | No | CLOSED | 1/15/2008 |
T-558 | Coil B-2 | Remove epoxy overflow fittings | Yes | CLOSED | 9/19/2007 |
T-540 | Coil B-2 | Fabricate Bushings | Yes | CLOSED | 9/27/2007 |
T-503 | Coil B-2 | Install batt insulation | Yes | QA CHECK | |
T-491 | Coil B-2 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-483 | Coil B-2 | Repair damaged cooling tubes | Yes | CLOSED | 10/12/2007 |
T-482 | Coil B-2 | Repair (6) threaded flange plugs (holes E19 through E26) | Yes | CLOSED | 9/4/2007 |
T-471 | Coil B-2 | Correct clamp interference (#60, 69) | Yes | CLOSED | 9/21/2007 |
T-442 | Coil B-2 | Add more fiducials | Yes | CLOSED | 6/14/2007 |
T-423 | Coil B-2 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 6/12/2007 |
T-405 | Coil B-2 | Check thread engagement on tapped holes | Yes | CLOSED | 6/12/2007 |
T-387 | Coil B-2 | Grinding/milling to accommodate nut access | Yes | CLOSED | 7/17/2007 |
T-369 | Coil B-2 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-351 | Coil B-2 | Grind overcasting | Yes | OPEN | |
T-333 | Coil B-2 | Metrology (pre-measurement) | Yes | CLOSED | 10/16/2007 |
T-281 | Coil B-2 | Documentation package complete and ready for copy | Yes | OPEN | |
T-263 | Coil B-2 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 6/26/2007 |
T-245 | Coil B-2 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 6/15/2007 |
T-227 | Coil B-2 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-209 | Coil B-2 | Install thermocouples (coil areas) | Yes | OPEN | |
T-191 | Coil B-2 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-173 | Coil B-2 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-150 | Coil B-2 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 10/18/2007 |
T-132 | Coil B-2 | Cover entire lead area with cover/box | No | OPEN | |
T-114 | Coil B-2 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 6/15/2007 |
T-080 | Coil B-2 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-046 | Coil B-2 | Cut fingers of top chill plates | Yes | CLOSED | 4/2/2007 |
T-584 | Coil B-3 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-569 | Coil B-3 | Secure terminal lug hardware | No | CLOSED | 12/7/2007 |
T-564 | Coil B-3 | Re-tap hole E18. Bottom half-filled with epoxy. | Yes | CLOSED | 10/22/2007 |
T-559 | Coil B-3 | Remove epoxy overflow fittings | Yes | CLOSED | 10/22/2007 |
T-541 | Coil B-3 | Fabricate Bushings | Yes | CLOSED | 10/11/2007 |
T-504 | Coil B-3 | Install batt insulation | Yes | OPEN | |
T-492 | Coil B-3 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-472 | Coil B-3 | Correct clamp interference (#60, 69) | Yes | CLOSED | 8/24/2007 |
T-443 | Coil B-3 | Add more fiducials | Yes | CLOSED | 10/29/2007 |
T-424 | Coil B-3 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 9/4/2007 |
T-406 | Coil B-3 | Check thread engagement on tapped holes | Yes | CLOSED | 9/4/2007 |
T-388 | Coil B-3 | Grinding/milling to accommodate nut access | Yes | CLOSED | 10/22/2007 |
T-370 | Coil B-3 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-352 | Coil B-3 | Grind overcasting | Yes | OPEN | |
T-334 | Coil B-3 | Metrology (pre-measurement) | Yes | CLOSED | 12/5/2007 |
T-282 | Coil B-3 | Documentation package complete and ready for copy | Yes | OPEN | |
T-264 | Coil B-3 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 9/6/2007 |
T-246 | Coil B-3 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 8/24/2007 |
T-228 | Coil B-3 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-210 | Coil B-3 | Install thermocouples (coil areas) | Yes | OPEN | |
T-192 | Coil B-3 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-174 | Coil B-3 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-151 | Coil B-3 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 12/7/2007 |
T-133 | Coil B-3 | Cover entire lead area with cover/box | No | OPEN | |
T-115 | Coil B-3 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 9/10/2007 |
T-097 | Coil B-3 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | CLOSED | 9/10/2007 |
T-089 | Coil B-3 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | CLOSED | 9/10/2007 |
T-081 | Coil B-3 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-063 | Coil B-3 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | OPEN | |
T-055 | Coil B-3 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | CLOSED | 4/2/2007 |
T-047 | Coil B-3 | Cut fingers of top chill plates | Yes | CLOSED | 8/24/2007 |
T-585 | Coil B-4 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-570 | Coil B-4 | Secure terminal lug hardware | No | CLOSED | 1/15/2008 |
T-560 | Coil B-4 | Remove epoxy overflow fittings | Yes | CLOSED | 12/7/2007 |
T-542 | Coil B-4 | Fabricate Bushings | Yes | CLOSED | 10/25/2007 |
T-505 | Coil B-4 | Install batt insulation | Yes | OPEN | |
T-493 | Coil B-4 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-473 | Coil B-4 | Correct clamp interference (#60, 69) | Yes | CLOSED | 10/3/2007 |
T-453 | Coil B-4 | Remove supplier's tooling ball inserts | Yes | OPEN | |
T-444 | Coil B-4 | Add more fiducials | Yes | CLOSED | 12/4/2007 |
T-425 | Coil B-4 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-407 | Coil B-4 | Check thread engagement on tapped holes | Yes | OPEN | |
T-389 | Coil B-4 | Grinding/milling to accommodate nut access | Yes | CLOSED | 12/7/2007 |
T-371 | Coil B-4 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-353 | Coil B-4 | Grind overcasting | Yes | OPEN | |
T-335 | Coil B-4 | Metrology (pre-measurement) | Yes | CLOSED | 12/18/2007 |
T-283 | Coil B-4 | Documentation package complete and ready for copy | Yes | OPEN | |
T-265 | Coil B-4 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 10/3/2007 |
T-247 | Coil B-4 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 10/3/2007 |
T-229 | Coil B-4 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 1/15/2008 |
T-211 | Coil B-4 | Install thermocouples (coil areas) | Yes | QA CHECK | |
T-193 | Coil B-4 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-175 | Coil B-4 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-152 | Coil B-4 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 1/15/2008 |
T-134 | Coil B-4 | Cover entire lead area with cover/box | No | OPEN | |
T-116 | Coil B-4 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 10/3/2007 |
T-098 | Coil B-4 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | CLOSED | 10/3/2007 |
T-090 | Coil B-4 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | CLOSED | 10/3/2007 |
T-082 | Coil B-4 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-064 | Coil B-4 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | CLOSED | 1/15/2008 |
T-056 | Coil B-4 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | CLOSED | 10/3/2007 |
T-048 | Coil B-4 | Cut fingers of top chill plates | Yes | CLOSED | 10/3/2007 |
T-586 | Coil B-5 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-571 | Coil B-5 | Secure terminal lug hardware | No | OPEN | |
T-561 | Coil B-5 | Remove epoxy overflow fittings | Yes | OPEN | |
T-543 | Coil B-5 | Fabricate Bushings | Yes | OPEN | |
T-506 | Coil B-5 | Install batt insulation | Yes | OPEN | |
T-494 | Coil B-5 | Complete electrical tests following VPI | Yes | OPEN | |
T-474 | Coil B-5 | Correct clamp interference (#60, 69) | Yes | OPEN | |
T-445 | Coil B-5 | Add more fiducials | Yes | OPEN | |
T-434 | Coil B-5 | Remove supplier's tooling ball inserts | Yes | OPEN | |
T-426 | Coil B-5 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-408 | Coil B-5 | Check thread engagement on tapped holes | Yes | OPEN | |
T-390 | Coil B-5 | Grinding/milling to accommodate nut access | Yes | OPEN | |
T-372 | Coil B-5 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-354 | Coil B-5 | Grind overcasting | Yes | OPEN | |
T-336 | Coil B-5 | Metrology (pre-measurement) | Yes | OPEN | |
T-284 | Coil B-5 | Documentation package complete and ready for copy | Yes | OPEN | |
T-266 | Coil B-5 | Mount final co-wound diagnostic box to casting | Yes | OPEN | |
T-248 | Coil B-5 | Lock all clamp hardware- weld locking wire | Yes | OPEN | |
T-230 | Coil B-5 | Modify final coil clamps- permeability & fitup issues | Yes | OPEN | |
T-212 | Coil B-5 | Install thermocouples (coil areas) | Yes | OPEN | |
T-194 | Coil B-5 | Install strain gauges- fiber optic | Yes | OPEN | |
T-176 | Coil B-5 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-153 | Coil B-5 | Tie poloidal break shims & bolts electrically to the winding form | No | OPEN | |
T-135 | Coil B-5 | Cover entire lead area with cover/box | No | OPEN | |
T-117 | Coil B-5 | Electrically tie the three jumper studs to the bottom jumper | No | OPEN | |
T-099 | Coil B-5 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | OPEN | |
T-091 | Coil B-5 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | OPEN | |
T-083 | Coil B-5 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-065 | Coil B-5 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | OPEN | |
T-057 | Coil B-5 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | OPEN | |
T-049 | Coil B-5 | Cut fingers of top chill plates | Yes | OPEN | |
T-587 | Coil B-6 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-572 | Coil B-6 | Secure terminal lug hardware | No | OPEN | |
T-562 | Coil B-6 | Remove epoxy overflow fittings | Yes | OPEN | |
T-544 | Coil B-6 | Fabricate Bushings | Yes | OPEN | |
T-507 | Coil B-6 | Install batt insulation | Yes | OPEN | |
T-495 | Coil B-6 | Complete electrical tests following VPI | Yes | OPEN | |
T-475 | Coil B-6 | Correct clamp interference (#60, 69) | Yes | OPEN | |
T-446 | Coil B-6 | Add more fiducials | Yes | CLOSED | 7/17/2007 |
T-427 | Coil B-6 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-409 | Coil B-6 | Check thread engagement on tapped holes | Yes | OPEN | |
T-391 | Coil B-6 | Grinding/milling to accommodate nut access | Yes | OPEN | |
T-373 | Coil B-6 | Add additional bolt holes | Yes | CLOSED | 7/26/2007 |
T-355 | Coil B-6 | Grind overcasting | Yes | OPEN | |
T-337 | Coil B-6 | Metrology (pre-measurement) | Yes | OPEN | |
T-285 | Coil B-6 | Documentation package complete and ready for copy | Yes | OPEN | |
T-267 | Coil B-6 | Mount final co-wound diagnostic box to casting | Yes | OPEN | |
T-249 | Coil B-6 | Lock all clamp hardware- weld locking wire | Yes | OPEN | |
T-231 | Coil B-6 | Modify final coil clamps- permeability & fitup issues | Yes | OPEN | |
T-213 | Coil B-6 | Install thermocouples (coil areas) | Yes | OPEN | |
T-195 | Coil B-6 | Install strain gauges- fiber optic | Yes | OPEN | |
T-177 | Coil B-6 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-154 | Coil B-6 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 10/18/2007 |
T-136 | Coil B-6 | Cover entire lead area with cover/box | No | OPEN | |
T-118 | Coil B-6 | Electrically tie the three jumper studs to the bottom jumper | No | OPEN | |
T-100 | Coil B-6 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | OPEN | |
T-092 | Coil B-6 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | OPEN | |
T-084 | Coil B-6 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-066 | Coil B-6 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | OPEN | |
T-058 | Coil B-6 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | OPEN | |
T-050 | Coil B-6 | Cut fingers of top chill plates | Yes | OPEN | |
T-588 | Coil C-1 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-545 | Coil C-1 | Fabricate Bushings | Yes | CLOSED | 9/5/2007 |
T-532 | Coil C-1 | Sand/grind clamp pads (B-C side) clamps 69, 71 | Yes | CLOSED | 11/8/2007 |
T-508 | Coil C-1 | Install batt insulation | Yes | QA CHECK | |
T-476 | Coil C-1 | Correct clamp interference (#63, 65, 69, 71) | Yes | CLOSED | 9/17/2007 |
T-457 | Coil C-1 | Secure terminal lug hardware | No | OPEN | |
T-447 | Coil C-1 | Add more fiducials | Yes | CLOSED | 4/24/2007 |
T-428 | Coil C-1 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 4/19/2007 |
T-410 | Coil C-1 | Check thread engagement on tapped holes | Yes | CLOSED | 4/19/2007 |
T-392 | Coil C-1 | Grinding/milling to accommodate nut access | Yes | CLOSED | 6/6/2007 |
T-374 | Coil C-1 | Add additional bolt holes (C-C) | Yes | CLOSED | 11/19/2007 |
T-356 | Coil C-1 | Grind overcasting | Yes | CLOSED | 1/11/2008 |
T-338 | Coil C-1 | Metrology (pre-measurement) | Yes | CLOSED | 9/13/2007 |
T-312 | Coil C-1 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-311 | Coil C-1 | Remove epoxy overflow fittings | Yes | CLOSED | 4/12/2007 |
T-310 | Coil C-1 | Adjust cooling tubes for coil to coil fit | Yes | CLOSED | 10/26/2007 |
T-268 | Coil C-1 | Documentation package complete and ready for copy | Yes | OPEN | |
T-250 | Coil C-1 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 4/19/2007 |
T-232 | Coil C-1 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 4/19/2007 |
T-214 | Coil C-1 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-196 | Coil C-1 | Install thermocouples (coil areas) | Yes | CLOSED | 1/10/2008 |
T-178 | Coil C-1 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-160 | Coil C-1 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-137 | Coil C-1 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 11/8/2007 |
T-119 | Coil C-1 | Cover entire lead area with cover/box | No | OPEN | |
T-101 | Coil C-1 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 4/19/2007 |
T-067 | Coil C-1 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-003 | Coil C-1 | Over stock castings- use gauge block and grind clearances as necessary (Type C coils) | Yes | CLOSED | 6/15/2007 |
T-002 | Coil C-1 | Correct holes in C-1 flange | | CLOSED | 3/27/2007 |
T-001 | Coil C-1 | Change poloidal break hardware | | CLOSED | 3/27/2007 |
T-589 | Coil C-2 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-573 | Coil C-2 | Remove epoxy overflow fittings | Yes | CLOSED | 11/13/2007 |
T-546 | Coil C-2 | Fabricate Bushings | Yes | CLOSED | 9/26/2007 |
T-509 | Coil C-2 | Install batt insulation | Yes | OPEN | |
T-477 | Coil C-2 | Correct clamp interference (#63, 65, 69, 71) | Yes | CLOSED | 8/24/2007 |
T-458 | Coil C-2 | Secure terminal lug hardware | No | CLOSED | 11/12/2007 |
T-448 | Coil C-2 | Add more fiducials | Yes | CLOSED | 10/30/2007 |
T-429 | Coil C-2 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 11/12/2007 |
T-411 | Coil C-2 | Check thread engagement on tapped holes | Yes | CLOSED | 11/12/2007 |
T-393 | Coil C-2 | Grinding/milling to accommodate nut access | Yes | CLOSED | 6/20/2007 |
T-375 | Coil C-2 | Add additional bolt holes (C-C) | Yes | CLOSED | 11/19/2007 |
T-357 | Coil C-2 | Grind overcasting | Yes | OPEN | |
T-339 | Coil C-2 | Metrology (pre-measurement) | Yes | CLOSED | 11/8/2007 |
T-325 | Coil C-2 | Remove epoxy overflow fitting | Yes | CLOSED | 4/2/2007 |
T-324 | Coil C-2 | Grind poloidal bk. winding clamp stud | | OPEN | |
T-323 | Coil C-2 | Adjust cooling tubes for coil to coil fit | | OPEN | |
T-322 | Coil C-2 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-269 | Coil C-2 | Documentation package complete and ready for copy | Yes | OPEN | |
T-251 | Coil C-2 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 4/10/2007 |
T-233 | Coil C-2 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 4/10/2007 |
T-215 | Coil C-2 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-197 | Coil C-2 | Install thermocouples (coil areas) | Yes | OPEN | |
T-179 | Coil C-2 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-161 | Coil C-2 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-138 | Coil C-2 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 11/12/2007 |
T-120 | Coil C-2 | Cover entire lead area with cover/box | No | OPEN | |
T-102 | Coil C-2 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 11/12/2007 |
T-068 | Coil C-2 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-037 | Coil C-2 | Cut fingers of top chill plates | Yes | CLOSED | 3/27/2007 |
T-004 | Coil C-2 | Over stock castings- use gauge block and grind clearances as necessary (Type C coils) | Yes | CLOSED | 11/12/2007 |
T-590 | Coil C-3 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-547 | Coil C-3 | Fabricate Bushings | Yes | CLOSED | 10/12/2007 |
T-510 | Coil C-3 | Install batt insulation | Yes | OPEN | |
T-478 | Coil C-3 | Correct clamp interference (#63, 65, 69, 71) | Yes | CLOSED | 8/24/2007 |
T-459 | Coil C-3 | Secure terminal lug hardware | No | OPEN | |
T-449 | Coil C-3 | Add more fiducials | Yes | OPEN | |
T-430 | Coil C-3 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-412 | Coil C-3 | Check thread engagement on tapped holes | Yes | OPEN | |
T-394 | Coil C-3 | Grinding/milling to accommodate nut access | Yes | CLOSED | 1/15/2008 |
T-376 | Coil C-3 | Add additional bolt holes (C-C) | Yes | CLOSED | 12/17/2007 |
T-358 | Coil C-3 | Grind overcasting | Yes | OPEN | |
T-340 | Coil C-3 | Metrology (pre-measurement) | Yes | OPEN | |
T-308 | Coil C-3 | Remove epoxy overflow fittings | Yes | CLOSED | 12/17/2007 |
T-307 | Coil C-3 | Adjust cooling tubes for coil to coil fit | | OPEN | |
T-306 | Coil C-3 | Remove broken bolt in base of winding form | Yes | CLOSED | 8/24/2007 |
T-305 | Coil C-3 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-270 | Coil C-3 | Documentation package complete and ready for copy | Yes | OPEN | |
T-252 | Coil C-3 | Mount final co-wound diagnostic box to casting | Yes | OPEN | |
T-234 | Coil C-3 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 8/24/2007 |
T-216 | Coil C-3 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-198 | Coil C-3 | Install thermocouples (coil areas) | Yes | OPEN | |
T-180 | Coil C-3 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-162 | Coil C-3 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-139 | Coil C-3 | Tie poloidal break shims & bolts electrically to the winding form | No | OPEN | |
T-121 | Coil C-3 | Cover entire lead area with cover/box | No | OPEN | |
T-103 | Coil C-3 | Electrically tie the three jumper studs to the bottom jumper | No | OPEN | |
T-069 | Coil C-3 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-005 | Coil C-3 | Over stock castings- use gauge block and grind clearances as necessary (Type C coils) | Yes | OPEN | |
T-591 | Coil C-4 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-548 | Coil C-4 | Fabricate Bushings | Yes | OPEN | |
T-511 | Coil C-4 | Install batt insulation | Yes | OPEN | |
T-479 | Coil C-4 | Correct clamp interference (#63, 65, 69, 71) | Yes | OPEN | |
T-460 | Coil C-4 | Secure terminal lug hardware | No | OPEN | |
T-450 | Coil C-4 | Add more fiducials | Yes | OPEN | |
T-431 | Coil C-4 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 5/29/2007 |
T-413 | Coil C-4 | Check thread engagement on tapped holes | Yes | CLOSED | 5/29/2007 |
T-395 | Coil C-4 | Grinding/milling to accommodate nut access | Yes | OPEN | |
T-377 | Coil C-4 | Add additional bolt holes (C-C) | Yes | OPEN | |
T-359 | Coil C-4 | Grind overcasting | Yes | OPEN | |
T-341 | Coil C-4 | Metrology (pre-measurement) | Yes | OPEN | |
T-316 | Coil C-4 | Adjust cooling tubes for coil to coil fit | | OPEN | |
T-315 | Coil C-4 | Remove epoxy overflow fittings | Yes | OPEN | |
T-314 | Coil C-4 | Replace damaged co-wound loop | Yes | CLOSED | 7/17/2007 |
T-313 | Coil C-4 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-271 | Coil C-4 | Documentation package complete and ready for copy | Yes | OPEN | |
T-253 | Coil C-4 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 7/17/2007 |
T-235 | Coil C-4 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 7/17/2007 |
T-217 | Coil C-4 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-199 | Coil C-4 | Install thermocouples (coil areas) | Yes | OPEN | |
T-181 | Coil C-4 | Install strain gauges- fiber optic | Yes | CLOSED | 8/13/2007 |
T-163 | Coil C-4 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-140 | Coil C-4 | Tie poloidal break shims & bolts electrically to the winding form | No | OPEN | |
T-122 | Coil C-4 | Cover entire lead area with cover/box | No | OPEN | |
T-104 | Coil C-4 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 6/15/2007 |
T-070 | Coil C-4 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-007 | Coil C-4 | Replace damaged co-wound loop side B [C4] | Yes | CLOSED | 7/17/2007 |
T-592 | Coil C-5 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-549 | Coil C-5 | Fabricate Bushings | Yes | CLOSED | 10/25/2007 |
T-512 | Coil C-5 | Install batt insulation | Yes | OPEN | |
T-484 | Coil C-5 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-480 | Coil C-5 | Correct clamp interference (#63, 65, 69, 71) | Yes | CLOSED | 1/15/2008 |
T-461 | Coil C-5 | Secure terminal lug hardware | No | CLOSED | 1/15/2008 |
T-451 | Coil C-5 | Add more fiducials | Yes | CLOSED | 5/2/2007 |
T-432 | Coil C-5 | Check threads (run bolt through) on tapped holes | Yes | CLOSED | 4/19/2007 |
T-414 | Coil C-5 | Check thread engagement on tapped holes | Yes | CLOSED | 4/19/2007 |
T-396 | Coil C-5 | Grinding/milling to accommodate nut access | Yes | OPEN | |
T-378 | Coil C-5 | Add additional bolt holes (C-C) | Yes | OPEN | |
T-360 | Coil C-5 | Grind overcasting | Yes | OPEN | |
T-342 | Coil C-5 | Metrology (pre-measurement) | Yes | CLOSED | 10/26/2007 |
T-319 | Coil C-5 | Adjust cooling tubes for coil to coil fit | Yes | OPEN | |
T-318 | Coil C-5 | Remove epoxy overflow fittings | Yes | CLOSED | 4/2/2007 |
T-317 | Coil C-5 | Complete electrical tests following VPI | Yes | CLOSED | 12/12/2007 |
T-272 | Coil C-5 | Documentation package complete and ready for copy | Yes | OPEN | |
T-254 | Coil C-5 | Mount final co-wound diagnostic box to casting | Yes | CLOSED | 4/10/2007 |
T-236 | Coil C-5 | Lock all clamp hardware- weld locking wire | Yes | CLOSED | 4/10/2007 |
T-218 | Coil C-5 | Modify final coil clamps- permeability & fitup issues | Yes | CLOSED | 11/8/2007 |
T-200 | Coil C-5 | Install thermocouples (coil areas) | Yes | QA CHECK | |
T-182 | Coil C-5 | Install strain gauges- fiber optic | Yes | OPEN | |
T-164 | Coil C-5 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-141 | Coil C-5 | Tie poloidal break shims & bolts electrically to the winding form | No | CLOSED | 10/18/2007 |
T-123 | Coil C-5 | Cover entire lead area with cover/box | No | OPEN | |
T-105 | Coil C-5 | Electrically tie the three jumper studs to the bottom jumper | No | CLOSED | 1/15/2008 |
T-071 | Coil C-5 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-593 | Coil C-6 | Electrical test (7.5 kV) following winding form re-work | Yes | OPEN | |
T-563 | Coil C-6 | Remove epoxy overflow fittings | Yes | OPEN | |
T-550 | Coil C-6 | Fabricate Bushings | Yes | OPEN | |
T-513 | Coil C-6 | Install batt insulation | Yes | OPEN | |
T-485 | Coil C-6 | Complete electrical tests following VPI | Yes | OPEN | |
T-481 | Coil C-6 | Correct clamp interference (#63, 65, 69, 71) | Yes | OPEN | |
T-462 | Coil C-6 | Secure terminal lug hardware | No | OPEN | |
T-452 | Coil C-6 | Add more fiducials | Yes | OPEN | |
T-433 | Coil C-6 | Check threads (run bolt through) on tapped holes | Yes | OPEN | |
T-415 | Coil C-6 | Check thread engagement on tapped holes | Yes | OPEN | |
T-397 | Coil C-6 | Grinding/milling to accommodate nut access | Yes | OPEN | |
T-379 | Coil C-6 | Add additional bolt holes (C-C) | Yes | OPEN | |
T-361 | Coil C-6 | Grind overcasting | Yes | OPEN | |
T-343 | Coil C-6 | Metrology (pre-measurement) | Yes | OPEN | |
T-273 | Coil C-6 | Documentation package complete and ready for copy | Yes | OPEN | |
T-255 | Coil C-6 | Mount final co-wound diagnostic box to casting | Yes | OPEN | |
T-237 | Coil C-6 | Lock all clamp hardware- weld locking wire | Yes | OPEN | |
T-219 | Coil C-6 | Modify final coil clamps- permeability & fitup issues | Yes | OPEN | |
T-201 | Coil C-6 | Install thermocouples (coil areas) | Yes | OPEN | |
T-183 | Coil C-6 | Install strain gauges- fiber optic | Yes | OPEN | |
T-165 | Coil C-6 | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | No | OPEN | |
T-142 | Coil C-6 | Tie poloidal break shims & bolts electrically to the winding form | No | OPEN | |
T-124 | Coil C-6 | Cover entire lead area with cover/box | No | OPEN | |
T-106 | Coil C-6 | Electrically tie the three jumper studs to the bottom jumper | No | OPEN | |
T-093 | Coil C-6 | Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plate | Yes | OPEN | |
T-085 | Coil C-6 | Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distance | Yes | OPEN | |
T-072 | Coil C-6 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | No | OPEN | |
T-059 | Coil C-6 | In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking path | No | OPEN | |
T-051 | Coil C-6 | Replace chill plates in lead and poloidal break areas with G-11 spacers | Yes | OPEN | |
T-038 | Coil C-6 | Cut fingers of top chill plates | Yes | OPEN | |
T-006 | Coil C-6 | Over stock castings- use gauge block and grind clearances as necessary (Type C coils) | Yes | OPEN | |
T-575 | VVSA-1 | A1 to A2 gross fit test | Yes | CLOSED | 12/3/2007 |
T-519 | VVSA-1 | C2 to C3 gross fit test | Yes | CLOSED | 1/15/2008 |
T-518 | VVSA-1 | B2 to C2 gross fit test | Yes | OPEN | |
T-517 | VVSA-1 | A2 to B2 gross fit test | Yes | OPEN | |
T-516 | VVSA-1 | C1 to C5 gross fit test | Yes | CLOSED | 10/26/2007 |
T-515 | VVSA-1 | B1 to C1 gross fit test | Yes | CLOSED | 1/8/2008 |
T-514 | VVSA-1 | A1 to B1 gross fit test | Yes | CLOSED | 7/26/2007 |
T-525 | VVSA-2 | C4 to C6 gross fit test | Yes | OPEN | |
T-524 | VVSA-2 | B4 to C4 gross fit test | Yes | OPEN | |
T-523 | VVSA-2 | A4 to B4 gross fit test | Yes | OPEN | |
T-522 | VVSA-2 | A3 to A4 gross fit test | Yes | OPEN | |
T-521 | VVSA-2 | B3 to C3 gross fit test | Yes | OPEN | |
T-520 | VVSA-2 | A3 to B3 gross fit test | Yes | OPEN | |
T-530 | VVSA-3 | B6 to C5 gross fit test | Yes | OPEN | |
T-529 | VVSA-3 | A6 to B6 gross fit test | Yes | OPEN | |
T-528 | VVSA-3 | A5 to A6 gross fit test | Yes | OPEN | |
T-527 | VVSA-3 | B5 to C6 gross fit test | Yes | OPEN | |
T-526 | VVSA-3 | A5 to B5 gross fit test | Yes | OPEN | |
FileMaker Pro Version: 8.0v3 |
Build: 03-20-2006 |