Database: NCSX PUNCHLIST.fp7
Records: 593
Task No.ItemDescriptionFPAStatusDate Closed
T-309NOT USEDCLOSED
T-304NOT USEDCLOSED
T-303NOT USEDCLOSED
T-302NOT USEDCLOSED
T-301NOT USEDCLOSED
T-300NOT USEDCLOSED
T-299NOT USEDCLOSED
T-298NOT USEDCLOSED
T-297NOT USEDCLOSED
T-296NOT USEDCLOSED
T-295NOT USEDCLOSED
T-294NOT USEDCLOSED
T-293NOT USEDCLOSED
T-292NOT USEDCLOSED
T-291NOT USEDCLOSED
T-290NOT USEDCLOSED
T-289NOT USEDCLOSED
T-288NOT USEDCLOSED
T-287NOT USEDCLOSED
T-286NOT USEDCLOSED
T-036NOT USEDNoCLOSED
T-035NOT USEDNoCLOSED
T-034NOT USEDNoCLOSED
T-033NOT USEDNoCLOSED
T-032NOT USEDNoCLOSED
T-031NOT USEDNoCLOSED
T-030NOT USEDNoCLOSED
T-029NOT USEDNoCLOSED
T-028NOT USEDNoCLOSED
T-027NOT USEDNoCLOSED
T-026NOT USEDNoCLOSED
T-025NOT USEDNoCLOSED
T-024NOT USEDNoCLOSED
T-023NOT USEDNoCLOSED
T-022NOT USEDNoCLOSED
T-021NOT USEDNoCLOSED
T-020NOT USEDNoCLOSED
T-019NOT USEDNoCLOSED
T-018NOT USEDYesCLOSED
T-017NOT USEDYesCLOSED
T-016NOT USEDYesCLOSED
T-015NOT USEDYesCLOSED
T-014NOT USEDYesCLOSED
T-013NOT USEDYesCLOSED
T-012NOT USEDYesCLOSED
T-011NOT USEDYesCLOSED
T-010NOT USEDNoCLOSED
T-009NOT USEDYesCLOSED
T-008NOT USEDYesCLOSED
T-576Coil A-1Electrical test (7.5 kV) following winding form re-workYesCLOSED1/8/2008
T-551Coil A-1Remove epoxy overflow fittingsYesCLOSED9/6/2007
T-533Coil A-1Fabricate BushingsYesCLOSED9/7/2007
T-496Coil A-1Install batt insulationYesQA CHECK
T-464Coil A-1Correct clamp interference (#59, 61)YesCLOSED9/6/2007
T-454Coil A-1Secure terminal lug hardwareNoCLOSED10/25/2007
T-416Coil A-1Check threads (run bolt through) on tapped holesYesCLOSED5/22/2007
T-398Coil A-1Check thread engagement on tapped holesYesCLOSED5/22/2007
T-380Coil A-1Grinding/milling to accommodate nut accessYesCLOSED8/24/2007
T-362Coil A-1Add additional bolt holesYesCLOSED7/26/2007
T-344Coil A-1Grind overcastingYesCLOSED6/15/2007
T-326Coil A-1Metrology (pre-measurement) also scan coil to vessel boss connectionYesCLOSED10/5/2007
T-321Coil A-1Repair (2) threaded flange plugsYesCLOSED8/24/2007
T-320Coil A-1Complete electrical tests following VPIYesCLOSED12/12/2007
T-274Coil A-1Documentation package complete and ready for copyYesOPEN
T-256Coil A-1Mount final co-wound diagnostic box to castingYesCLOSED4/12/2007
T-238Coil A-1Lock all clamp hardware- weld locking wireYesCLOSED4/12/2007
T-220Coil A-1Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-202Coil A-1Install thermocouples (coil areas)YesCLOSED1/10/2008
T-184Coil A-1Install strain gauges- fiber opticYesCLOSED8/13/2007
T-166Coil A-1Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-155Coil A-1Grind wing area type A coilsYesCLOSED5/29/2007
T-143Coil A-1Tie poloidal break shims & bolts electrically to the winding formNoCLOSED10/18/2007
T-125Coil A-1Cover entire lead area with cover/boxNoOPEN
T-107Coil A-1Electrically tie the three jumper studs to the bottom jumperNoCLOSED10/22/2007
T-073Coil A-1Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-039Coil A-1Cut fingers of top chill platesYesCLOSED4/2/2007
T-577Coil A-2Electrical test (7.5 kV) following winding form re-workYesOPEN
T-574Coil A-2Repair damaged cooling tubesYesCLOSED10/22/2007
T-552Coil A-2Remove epoxy overflow fittingsYesCLOSED10/3/2007
T-534Coil A-2Fabricate BushingsYesCLOSED9/27/2007
T-497Coil A-2Install batt insulationYesQA CHECK
T-486Coil A-2Complete electrical tests following VPIYesCLOSED12/12/2007
T-465Coil A-2Correct clamp interference (#59, 61)YesCLOSED10/22/2007
T-455Coil A-2Secure terminal lug hardwareNoCLOSED10/24/2007
T-417Coil A-2Check threads (run bolt through) on tapped holesYesCLOSED6/26/2007
T-399Coil A-2Check thread engagement on tapped holesYesCLOSED6/26/2007
T-381Coil A-2Grinding/milling to accommodate nut accessYesCLOSED7/20/2007
T-363Coil A-2Add additional bolt holesYesCLOSED7/26/2007
T-345Coil A-2Grind overcastingYesOPEN
T-327Coil A-2Metrology (pre-measurement) also scan coil to vessel boss connectionYesCLOSED10/16/2007
T-275Coil A-2Documentation package complete and ready for copyYesOPEN
T-257Coil A-2Mount final co-wound diagnostic box to castingYesCLOSED6/15/2007
T-239Coil A-2Lock all clamp hardware- weld locking wireYesCLOSED6/15/2007
T-221Coil A-2Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-203Coil A-2Install thermocouples (coil areas)YesOPEN
T-185Coil A-2Install strain gauges- fiber opticYesCLOSED8/13/2007
T-167Coil A-2Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-156Coil A-2Grind wing area type A coilsYesCLOSED6/15/2007
T-144Coil A-2Tie poloidal break shims & bolts electrically to the winding formNoCLOSED10/22/2007
T-126Coil A-2Cover entire lead area with cover/boxNoOPEN
T-108Coil A-2Electrically tie the three jumper studs to the bottom jumperNoCLOSED6/15/2007
T-074Coil A-2Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-040Coil A-2Cut fingers of top chill platesYesCLOSED6/15/2007
T-578Coil A-3Electrical test (7.5 kV) following winding form re-workYesOPEN
T-553Coil A-3Remove epoxy overflow fittingsYesCLOSED12/7/2007
T-535Coil A-3Fabricate BushingsYesCLOSED10/12/2007
T-498Coil A-3Install batt insulationYesQA CHECK
T-487Coil A-3Complete electrical tests following VPIYesCLOSED12/12/2007
T-466Coil A-3Correct clamp interference (#59, 61)YesCLOSED8/20/2007
T-456Coil A-3Secure terminal lug hardwareNoCLOSED12/7/2007
T-437Coil A-3Add more fiducialsYesCLOSED11/13/2007
T-418Coil A-3Check threads (run bolt through) on tapped holesYesCLOSED4/20/2007
T-400Coil A-3Check thread engagement on tapped holesYesCLOSED4/20/2007
T-382Coil A-3Grinding/milling to accommodate nut accessYesCLOSED9/6/2007
T-364Coil A-3Add additional bolt holesYesCLOSED7/26/2007
T-346Coil A-3Grind overcastingYesCLOSED9/6/2007
T-328Coil A-3Metrology (pre-measurement) also scan coil to vessel boss connectionYesCLOSED12/5/2007
T-276Coil A-3Documentation package complete and ready for copyYesOPEN
T-258Coil A-3Mount final co-wound diagnostic box to castingYesCLOSED8/15/2007
T-240Coil A-3Lock all clamp hardware- weld locking wireYesCLOSED4/12/2007
T-222Coil A-3Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-204Coil A-3Install thermocouples (coil areas)YesOPEN
T-186Coil A-3Install strain gauges- fiber opticYesCLOSED8/13/2007
T-168Coil A-3Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-145Coil A-3Tie poloidal break shims & bolts electrically to the winding formNoCLOSED12/7/2007
T-127Coil A-3Cover entire lead area with cover/boxNoOPEN
T-109Coil A-3Electrically tie the three jumper studs to the bottom jumperNoCLOSED12/7/2007
T-075Coil A-3Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-041Coil A-3Cut fingers of top chill platesYesCLOSED4/2/2007
T-579Coil A-4Electrical test (7.5 kV) following winding form re-workYesOPEN
T-565Coil A-4Secure terminal lug hardwareNoCLOSED12/18/2007
T-554Coil A-4Remove epoxy overflow fittingsYesCLOSED9/7/2007
T-536Coil A-4Fabricate BushingsYesOPEN
T-531Coil A-4Repair dented cooling tube/RetestYesOPEN
T-499Coil A-4Install batt insulationYesOPEN
T-488Coil A-4Complete electrical tests following VPIYesCLOSED12/12/2007
T-467Coil A-4Correct clamp interference (#59, 61)YesOPEN
T-438Coil A-4Add more fiducialsYesCLOSED12/19/2007
T-419Coil A-4Check threads (run bolt through) on tapped holesYesCLOSED7/17/2007
T-401Coil A-4Check thread engagement on tapped holesYesCLOSED7/17/2007
T-383Coil A-4Grinding/milling to accommodate nut accessYesCLOSED9/7/2007
T-365Coil A-4Add additional bolt holesYesCLOSED7/26/2007
T-347Coil A-4Grind overcastingYesCLOSED9/7/2007
T-329Coil A-4Metrology (pre-measurement) also scan coil to vessel boss connectionYesOPEN
T-277Coil A-4Documentation package complete and ready for copyYesOPEN
T-259Coil A-4Mount final co-wound diagnostic box to castingYesCLOSED7/17/2007
T-241Coil A-4Lock all clamp hardware- weld locking wireYesCLOSED7/17/2007
T-223Coil A-4Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-205Coil A-4Install thermocouples (coil areas)YesOPEN
T-187Coil A-4Install strain gauges- fiber opticYesCLOSED8/13/2007
T-169Coil A-4Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-157Coil A-4Grind wing area type A coilsYesCLOSED9/7/2007
T-146Coil A-4Tie poloidal break shims & bolts electrically to the winding formNoCLOSED12/18/2007
T-128Coil A-4Cover entire lead area with cover/boxNoOPEN
T-110Coil A-4Electrically tie the three jumper studs to the bottom jumperNoCLOSED7/17/2007
T-094Coil A-4Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesCLOSED7/17/2007
T-086Coil A-4Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesCLOSED7/17/2007
T-076Coil A-4Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-060Coil A-4In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoCLOSED7/17/2007
T-052Coil A-4Replace chill plates in lead and poloidal break areas with G-11 spacersYesCLOSED4/2/2007
T-042Coil A-4Cut fingers of top chill platesYesCLOSED7/17/2007
T-580Coil A-5Electrical test (7.5 kV) following winding form re-workYesOPEN
T-566Coil A-5Secure terminal lug hardwareNoOPEN
T-555Coil A-5Remove epoxy overflow fittingsYesOPEN
T-537Coil A-5Fabricate BushingsYesCLOSED12/5/2007
T-500Coil A-5Install batt insulationYesQA CHECK
T-489Coil A-5Complete electrical tests following VPIYesCLOSED12/12/2007
T-468Coil A-5Correct clamp interference (#59, 61)YesCLOSED11/12/2007
T-439Coil A-5Add more fiducialsYesCLOSED12/4/2007
T-435Coil A-5Remove supplier's tooling ball insertsYesOPEN
T-420Coil A-5Check threads (run bolt through) on tapped holesYesOPEN
T-402Coil A-5Check thread engagement on tapped holesYesOPEN
T-384Coil A-5Grinding/milling to accommodate nut accessYesOPEN
T-366Coil A-5Add additional bolt holesYesCLOSED7/26/2007
T-348Coil A-5Grind overcastingYesOPEN
T-330Coil A-5Metrology (pre-measurement) also scan coil to vessel boss connectionYesCLOSED12/18/2007
T-278Coil A-5Documentation package complete and ready for copyYesOPEN
T-260Coil A-5Mount final co-wound diagnostic box to castingYesCLOSED12/7/2007
T-242Coil A-5Lock all clamp hardware- weld locking wireYesCLOSED11/12/2007
T-224Coil A-5Modify final coil clamps- permeability & fitup issuesYesCLOSED11/12/2007
T-206Coil A-5Install thermocouples (coil areas)YesOPEN
T-188Coil A-5Install strain gauges- fiber opticYesOPEN
T-170Coil A-5Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-158Coil A-5Grind wing area type A coilsYesOPEN
T-147Coil A-5Tie poloidal break shims & bolts electrically to the winding formNoCLOSED12/17/2007
T-129Coil A-5Cover entire lead area with cover/boxNoOPEN
T-111Coil A-5Electrically tie the three jumper studs to the bottom jumperNoCLOSED11/12/2007
T-095Coil A-5Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesCLOSED12/7/2007
T-087Coil A-5Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesCLOSED11/12/2007
T-077Coil A-5Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-061Coil A-5In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoOPEN
T-053Coil A-5Replace chill plates in lead and poloidal break areas with G-11 spacersYesCLOSED11/12/2007
T-043Coil A-5Cut fingers of top chill platesYesCLOSED11/12/2007
T-581Coil A-6Electrical test (7.5 kV) following winding form re-workYesOPEN
T-556Coil A-6Remove epoxy overflow fittingsYesOPEN
T-538Coil A-6Fabricate BushingsYesOPEN
T-501Coil A-6Install batt insulationYesOPEN
T-490Coil A-6Complete electrical tests following VPIYesOPEN
T-469Coil A-6Correct clamp interference (#59, 61)YesOPEN
T-440Coil A-6Add more fiducialsYesCLOSED7/17/2007
T-436Coil A-6Remove supplier's tooling ball insertsYesOPEN
T-421Coil A-6Check threads (run bolt through) on tapped holesYesOPEN
T-403Coil A-6Check thread engagement on tapped holesYesOPEN
T-385Coil A-6Grinding/milling to accommodate nut accessYesCLOSED10/5/2007
T-367Coil A-6Add additional bolt holesYesCLOSED7/26/2007
T-349Coil A-6Grind overcastingYesCLOSED12/17/2007
T-331Coil A-6Metrology (pre-measurement) also scan coil to vessel boss connectionYesOPEN
T-279Coil A-6Documentation package complete and ready for copyYesOPEN
T-261Coil A-6Mount final co-wound diagnostic box to castingYesOPEN
T-243Coil A-6Lock all clamp hardware- weld locking wireYesOPEN
T-225Coil A-6Modify final coil clamps- permeability & fitup issuesYesOPEN
T-207Coil A-6Install thermocouples (coil areas)YesOPEN
T-189Coil A-6Install strain gauges- fiber opticYesOPEN
T-171Coil A-6Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-159Coil A-6Grind wing area type A coilsYesCLOSED10/5/2007
T-148Coil A-6Tie poloidal break shims & bolts electrically to the winding formNoCLOSED11/8/2007
T-130Coil A-6Cover entire lead area with cover/boxNoOPEN
T-112Coil A-6Electrically tie the three jumper studs to the bottom jumperNoOPEN
T-096Coil A-6Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesOPEN
T-088Coil A-6Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesOPEN
T-078Coil A-6Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-062Coil A-6In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoOPEN
T-054Coil A-6Replace chill plates in lead and poloidal break areas with G-11 spacersYesOPEN
T-044Coil A-6Cut fingers of top chill platesYesOPEN
T-582Coil B-1Electrical test (7.5 kV) following winding form re-workYesCLOSED1/8/2008
T-567Coil B-1Secure terminal lug hardwareNoCLOSED11/8/2007
T-557Coil B-1Remove epoxy overflow fittingsYesCLOSED9/17/2007
T-539Coil B-1Fabricate BushingsYesCLOSED9/5/2007
T-502Coil B-1Install batt insulationYesOPEN
T-470Coil B-1Correct clamp interference (#60, 69)YesCLOSED8/21/2007
T-463Coil B-1Complete electrical tests following VPIYesCLOSED12/12/2007
T-441Coil B-1Add more fiducialsYesCLOSED5/7/2007
T-422Coil B-1Check threads (run bolt through) on tapped holesYesCLOSED5/24/2007
T-404Coil B-1Check thread engagement on tapped holesYesCLOSED5/24/2007
T-386Coil B-1Grinding/milling to accommodate nut accessYesCLOSED7/26/2007
T-368Coil B-1Add additional bolt holesYesCLOSED7/26/2007
T-350Coil B-1Grind overcastingYesCLOSED1/11/2008
T-332Coil B-1Metrology (pre-measurement)YesCLOSED8/7/2007
T-280Coil B-1Documentation package complete and ready for copyYesOPEN
T-262Coil B-1Mount final co-wound diagnostic box to castingYesCLOSED5/16/2007
T-244Coil B-1Lock all clamp hardware- weld locking wireYesCLOSED5/16/2007
T-226Coil B-1Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-208Coil B-1Install thermocouples (coil areas)YesCLOSED1/10/2008
T-190Coil B-1Install strain gauges- fiber opticYesCLOSED8/13/2007
T-172Coil B-1Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-149Coil B-1Tie poloidal break shims & bolts electrically to the winding formNoCLOSED11/8/2007
T-131Coil B-1Cover entire lead area with cover/boxNoOPEN
T-113Coil B-1Electrically tie the three jumper studs to the bottom jumperNoCLOSED5/16/2007
T-079Coil B-1Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-045Coil B-1Cut fingers of top chill platesYesCLOSED4/2/2007
T-583Coil B-2Electrical test (7.5 kV) following winding form re-workYesOPEN
T-568Coil B-2Secure terminal lug hardwareNoCLOSED1/15/2008
T-558Coil B-2Remove epoxy overflow fittingsYesCLOSED9/19/2007
T-540Coil B-2Fabricate BushingsYesCLOSED9/27/2007
T-503Coil B-2Install batt insulationYesQA CHECK
T-491Coil B-2Complete electrical tests following VPIYesCLOSED12/12/2007
T-483Coil B-2Repair damaged cooling tubesYesCLOSED10/12/2007
T-482Coil B-2Repair (6) threaded flange plugs (holes E19 through E26)YesCLOSED9/4/2007
T-471Coil B-2Correct clamp interference (#60, 69)YesCLOSED9/21/2007
T-442Coil B-2Add more fiducialsYesCLOSED6/14/2007
T-423Coil B-2Check threads (run bolt through) on tapped holesYesCLOSED6/12/2007
T-405Coil B-2Check thread engagement on tapped holesYesCLOSED6/12/2007
T-387Coil B-2Grinding/milling to accommodate nut accessYesCLOSED7/17/2007
T-369Coil B-2Add additional bolt holesYesCLOSED7/26/2007
T-351Coil B-2Grind overcastingYesOPEN
T-333Coil B-2Metrology (pre-measurement)YesCLOSED10/16/2007
T-281Coil B-2Documentation package complete and ready for copyYesOPEN
T-263Coil B-2Mount final co-wound diagnostic box to castingYesCLOSED6/26/2007
T-245Coil B-2Lock all clamp hardware- weld locking wireYesCLOSED6/15/2007
T-227Coil B-2Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-209Coil B-2Install thermocouples (coil areas)YesOPEN
T-191Coil B-2Install strain gauges- fiber opticYesCLOSED8/13/2007
T-173Coil B-2Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-150Coil B-2Tie poloidal break shims & bolts electrically to the winding formNoCLOSED10/18/2007
T-132Coil B-2Cover entire lead area with cover/boxNoOPEN
T-114Coil B-2Electrically tie the three jumper studs to the bottom jumperNoCLOSED6/15/2007
T-080Coil B-2Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-046Coil B-2Cut fingers of top chill platesYesCLOSED4/2/2007
T-584Coil B-3Electrical test (7.5 kV) following winding form re-workYesOPEN
T-569Coil B-3Secure terminal lug hardwareNoCLOSED12/7/2007
T-564Coil B-3Re-tap hole E18. Bottom half-filled with epoxy.YesCLOSED10/22/2007
T-559Coil B-3Remove epoxy overflow fittingsYesCLOSED10/22/2007
T-541Coil B-3Fabricate BushingsYesCLOSED10/11/2007
T-504Coil B-3Install batt insulationYesOPEN
T-492Coil B-3Complete electrical tests following VPIYesCLOSED12/12/2007
T-472Coil B-3Correct clamp interference (#60, 69)YesCLOSED8/24/2007
T-443Coil B-3Add more fiducialsYesCLOSED10/29/2007
T-424Coil B-3Check threads (run bolt through) on tapped holesYesCLOSED9/4/2007
T-406Coil B-3Check thread engagement on tapped holesYesCLOSED9/4/2007
T-388Coil B-3Grinding/milling to accommodate nut accessYesCLOSED10/22/2007
T-370Coil B-3Add additional bolt holesYesCLOSED7/26/2007
T-352Coil B-3Grind overcastingYesOPEN
T-334Coil B-3Metrology (pre-measurement)YesCLOSED12/5/2007
T-282Coil B-3Documentation package complete and ready for copyYesOPEN
T-264Coil B-3Mount final co-wound diagnostic box to castingYesCLOSED9/6/2007
T-246Coil B-3Lock all clamp hardware- weld locking wireYesCLOSED8/24/2007
T-228Coil B-3Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-210Coil B-3Install thermocouples (coil areas)YesOPEN
T-192Coil B-3Install strain gauges- fiber opticYesCLOSED8/13/2007
T-174Coil B-3Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-151Coil B-3Tie poloidal break shims & bolts electrically to the winding formNoCLOSED12/7/2007
T-133Coil B-3Cover entire lead area with cover/boxNoOPEN
T-115Coil B-3Electrically tie the three jumper studs to the bottom jumperNoCLOSED9/10/2007
T-097Coil B-3Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesCLOSED9/10/2007
T-089Coil B-3Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesCLOSED9/10/2007
T-081Coil B-3Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-063Coil B-3In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoOPEN
T-055Coil B-3Replace chill plates in lead and poloidal break areas with G-11 spacersYesCLOSED4/2/2007
T-047Coil B-3Cut fingers of top chill platesYesCLOSED8/24/2007
T-585Coil B-4Electrical test (7.5 kV) following winding form re-workYesOPEN
T-570Coil B-4Secure terminal lug hardwareNoCLOSED1/15/2008
T-560Coil B-4Remove epoxy overflow fittingsYesCLOSED12/7/2007
T-542Coil B-4Fabricate BushingsYesCLOSED10/25/2007
T-505Coil B-4Install batt insulationYesOPEN
T-493Coil B-4Complete electrical tests following VPIYesCLOSED12/12/2007
T-473Coil B-4Correct clamp interference (#60, 69)YesCLOSED10/3/2007
T-453Coil B-4Remove supplier's tooling ball insertsYesOPEN
T-444Coil B-4Add more fiducialsYesCLOSED12/4/2007
T-425Coil B-4Check threads (run bolt through) on tapped holesYesOPEN
T-407Coil B-4Check thread engagement on tapped holesYesOPEN
T-389Coil B-4Grinding/milling to accommodate nut accessYesCLOSED12/7/2007
T-371Coil B-4Add additional bolt holesYesCLOSED7/26/2007
T-353Coil B-4Grind overcastingYesOPEN
T-335Coil B-4Metrology (pre-measurement)YesCLOSED12/18/2007
T-283Coil B-4Documentation package complete and ready for copyYesOPEN
T-265Coil B-4Mount final co-wound diagnostic box to castingYesCLOSED10/3/2007
T-247Coil B-4Lock all clamp hardware- weld locking wireYesCLOSED10/3/2007
T-229Coil B-4Modify final coil clamps- permeability & fitup issuesYesCLOSED1/15/2008
T-211Coil B-4Install thermocouples (coil areas)YesQA CHECK
T-193Coil B-4Install strain gauges- fiber opticYesCLOSED8/13/2007
T-175Coil B-4Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-152Coil B-4Tie poloidal break shims & bolts electrically to the winding formNoCLOSED1/15/2008
T-134Coil B-4Cover entire lead area with cover/boxNoOPEN
T-116Coil B-4Electrically tie the three jumper studs to the bottom jumperNoCLOSED10/3/2007
T-098Coil B-4Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesCLOSED10/3/2007
T-090Coil B-4Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesCLOSED10/3/2007
T-082Coil B-4Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-064Coil B-4In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoCLOSED1/15/2008
T-056Coil B-4Replace chill plates in lead and poloidal break areas with G-11 spacersYesCLOSED10/3/2007
T-048Coil B-4Cut fingers of top chill platesYesCLOSED10/3/2007
T-586Coil B-5Electrical test (7.5 kV) following winding form re-workYesOPEN
T-571Coil B-5Secure terminal lug hardwareNoOPEN
T-561Coil B-5Remove epoxy overflow fittingsYesOPEN
T-543Coil B-5Fabricate BushingsYesOPEN
T-506Coil B-5Install batt insulationYesOPEN
T-494Coil B-5Complete electrical tests following VPIYesOPEN
T-474Coil B-5Correct clamp interference (#60, 69)YesOPEN
T-445Coil B-5Add more fiducialsYesOPEN
T-434Coil B-5Remove supplier's tooling ball insertsYesOPEN
T-426Coil B-5Check threads (run bolt through) on tapped holesYesOPEN
T-408Coil B-5Check thread engagement on tapped holesYesOPEN
T-390Coil B-5Grinding/milling to accommodate nut accessYesOPEN
T-372Coil B-5Add additional bolt holesYesCLOSED7/26/2007
T-354Coil B-5Grind overcastingYesOPEN
T-336Coil B-5Metrology (pre-measurement)YesOPEN
T-284Coil B-5Documentation package complete and ready for copyYesOPEN
T-266Coil B-5Mount final co-wound diagnostic box to castingYesOPEN
T-248Coil B-5Lock all clamp hardware- weld locking wireYesOPEN
T-230Coil B-5Modify final coil clamps- permeability & fitup issuesYesOPEN
T-212Coil B-5Install thermocouples (coil areas)YesOPEN
T-194Coil B-5Install strain gauges- fiber opticYesOPEN
T-176Coil B-5Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-153Coil B-5Tie poloidal break shims & bolts electrically to the winding formNoOPEN
T-135Coil B-5Cover entire lead area with cover/boxNoOPEN
T-117Coil B-5Electrically tie the three jumper studs to the bottom jumperNoOPEN
T-099Coil B-5Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesOPEN
T-091Coil B-5Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesOPEN
T-083Coil B-5Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-065Coil B-5In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoOPEN
T-057Coil B-5Replace chill plates in lead and poloidal break areas with G-11 spacersYesOPEN
T-049Coil B-5Cut fingers of top chill platesYesOPEN
T-587Coil B-6Electrical test (7.5 kV) following winding form re-workYesOPEN
T-572Coil B-6Secure terminal lug hardwareNoOPEN
T-562Coil B-6Remove epoxy overflow fittingsYesOPEN
T-544Coil B-6Fabricate BushingsYesOPEN
T-507Coil B-6Install batt insulationYesOPEN
T-495Coil B-6Complete electrical tests following VPIYesOPEN
T-475Coil B-6Correct clamp interference (#60, 69)YesOPEN
T-446Coil B-6Add more fiducialsYesCLOSED7/17/2007
T-427Coil B-6Check threads (run bolt through) on tapped holesYesOPEN
T-409Coil B-6Check thread engagement on tapped holesYesOPEN
T-391Coil B-6Grinding/milling to accommodate nut accessYesOPEN
T-373Coil B-6Add additional bolt holesYesCLOSED7/26/2007
T-355Coil B-6Grind overcastingYesOPEN
T-337Coil B-6Metrology (pre-measurement)YesOPEN
T-285Coil B-6Documentation package complete and ready for copyYesOPEN
T-267Coil B-6Mount final co-wound diagnostic box to castingYesOPEN
T-249Coil B-6Lock all clamp hardware- weld locking wireYesOPEN
T-231Coil B-6Modify final coil clamps- permeability & fitup issuesYesOPEN
T-213Coil B-6Install thermocouples (coil areas)YesOPEN
T-195Coil B-6Install strain gauges- fiber opticYesOPEN
T-177Coil B-6Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-154Coil B-6Tie poloidal break shims & bolts electrically to the winding formNoCLOSED10/18/2007
T-136Coil B-6Cover entire lead area with cover/boxNoOPEN
T-118Coil B-6Electrically tie the three jumper studs to the bottom jumperNoOPEN
T-100Coil B-6Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesOPEN
T-092Coil B-6Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesOPEN
T-084Coil B-6Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-066Coil B-6In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoOPEN
T-058Coil B-6Replace chill plates in lead and poloidal break areas with G-11 spacersYesOPEN
T-050Coil B-6Cut fingers of top chill platesYesOPEN
T-588Coil C-1Electrical test (7.5 kV) following winding form re-workYesOPEN
T-545Coil C-1Fabricate BushingsYesCLOSED9/5/2007
T-532Coil C-1Sand/grind clamp pads (B-C side) clamps 69, 71YesCLOSED11/8/2007
T-508Coil C-1Install batt insulationYesQA CHECK
T-476Coil C-1Correct clamp interference (#63, 65, 69, 71)YesCLOSED9/17/2007
T-457Coil C-1Secure terminal lug hardwareNoOPEN
T-447Coil C-1Add more fiducialsYesCLOSED4/24/2007
T-428Coil C-1Check threads (run bolt through) on tapped holesYesCLOSED4/19/2007
T-410Coil C-1Check thread engagement on tapped holesYesCLOSED4/19/2007
T-392Coil C-1Grinding/milling to accommodate nut accessYesCLOSED6/6/2007
T-374Coil C-1Add additional bolt holes (C-C)YesCLOSED11/19/2007
T-356Coil C-1Grind overcastingYesCLOSED1/11/2008
T-338Coil C-1Metrology (pre-measurement)YesCLOSED9/13/2007
T-312Coil C-1Complete electrical tests following VPIYesCLOSED12/12/2007
T-311Coil C-1Remove epoxy overflow fittingsYesCLOSED4/12/2007
T-310Coil C-1Adjust cooling tubes for coil to coil fitYesCLOSED10/26/2007
T-268Coil C-1Documentation package complete and ready for copyYesOPEN
T-250Coil C-1Mount final co-wound diagnostic box to castingYesCLOSED4/19/2007
T-232Coil C-1Lock all clamp hardware- weld locking wireYesCLOSED4/19/2007
T-214Coil C-1Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-196Coil C-1Install thermocouples (coil areas)YesCLOSED1/10/2008
T-178Coil C-1Install strain gauges- fiber opticYesCLOSED8/13/2007
T-160Coil C-1Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-137Coil C-1Tie poloidal break shims & bolts electrically to the winding formNoCLOSED11/8/2007
T-119Coil C-1Cover entire lead area with cover/boxNoOPEN
T-101Coil C-1Electrically tie the three jumper studs to the bottom jumperNoCLOSED4/19/2007
T-067Coil C-1Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-003Coil C-1Over stock castings- use gauge block and grind clearances as necessary (Type C coils)YesCLOSED6/15/2007
T-002Coil C-1Correct holes in C-1 flangeCLOSED3/27/2007
T-001Coil C-1Change poloidal break hardwareCLOSED3/27/2007
T-589Coil C-2Electrical test (7.5 kV) following winding form re-workYesOPEN
T-573Coil C-2Remove epoxy overflow fittingsYesCLOSED11/13/2007
T-546Coil C-2Fabricate BushingsYesCLOSED9/26/2007
T-509Coil C-2Install batt insulationYesOPEN
T-477Coil C-2Correct clamp interference (#63, 65, 69, 71)YesCLOSED8/24/2007
T-458Coil C-2Secure terminal lug hardwareNoCLOSED11/12/2007
T-448Coil C-2Add more fiducialsYesCLOSED10/30/2007
T-429Coil C-2Check threads (run bolt through) on tapped holesYesCLOSED11/12/2007
T-411Coil C-2Check thread engagement on tapped holesYesCLOSED11/12/2007
T-393Coil C-2Grinding/milling to accommodate nut accessYesCLOSED6/20/2007
T-375Coil C-2Add additional bolt holes (C-C)YesCLOSED11/19/2007
T-357Coil C-2Grind overcastingYesOPEN
T-339Coil C-2Metrology (pre-measurement)YesCLOSED11/8/2007
T-325Coil C-2Remove epoxy overflow fittingYesCLOSED4/2/2007
T-324Coil C-2Grind poloidal bk. winding clamp studOPEN
T-323Coil C-2Adjust cooling tubes for coil to coil fitOPEN
T-322Coil C-2Complete electrical tests following VPIYesCLOSED12/12/2007
T-269Coil C-2Documentation package complete and ready for copyYesOPEN
T-251Coil C-2Mount final co-wound diagnostic box to castingYesCLOSED4/10/2007
T-233Coil C-2Lock all clamp hardware- weld locking wireYesCLOSED4/10/2007
T-215Coil C-2Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-197Coil C-2Install thermocouples (coil areas)YesOPEN
T-179Coil C-2Install strain gauges- fiber opticYesCLOSED8/13/2007
T-161Coil C-2Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-138Coil C-2Tie poloidal break shims & bolts electrically to the winding formNoCLOSED11/12/2007
T-120Coil C-2Cover entire lead area with cover/boxNoOPEN
T-102Coil C-2Electrically tie the three jumper studs to the bottom jumperNoCLOSED11/12/2007
T-068Coil C-2Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-037Coil C-2Cut fingers of top chill platesYesCLOSED3/27/2007
T-004Coil C-2Over stock castings- use gauge block and grind clearances as necessary (Type C coils)YesCLOSED11/12/2007
T-590Coil C-3Electrical test (7.5 kV) following winding form re-workYesOPEN
T-547Coil C-3Fabricate BushingsYesCLOSED10/12/2007
T-510Coil C-3Install batt insulationYesOPEN
T-478Coil C-3Correct clamp interference (#63, 65, 69, 71)YesCLOSED8/24/2007
T-459Coil C-3Secure terminal lug hardwareNoOPEN
T-449Coil C-3Add more fiducialsYesOPEN
T-430Coil C-3Check threads (run bolt through) on tapped holesYesOPEN
T-412Coil C-3Check thread engagement on tapped holesYesOPEN
T-394Coil C-3Grinding/milling to accommodate nut accessYesCLOSED1/15/2008
T-376Coil C-3Add additional bolt holes (C-C)YesCLOSED12/17/2007
T-358Coil C-3Grind overcastingYesOPEN
T-340Coil C-3Metrology (pre-measurement)YesOPEN
T-308Coil C-3Remove epoxy overflow fittingsYesCLOSED12/17/2007
T-307Coil C-3Adjust cooling tubes for coil to coil fitOPEN
T-306Coil C-3Remove broken bolt in base of winding formYesCLOSED8/24/2007
T-305Coil C-3Complete electrical tests following VPIYesCLOSED12/12/2007
T-270Coil C-3Documentation package complete and ready for copyYesOPEN
T-252Coil C-3Mount final co-wound diagnostic box to castingYesOPEN
T-234Coil C-3Lock all clamp hardware- weld locking wireYesCLOSED8/24/2007
T-216Coil C-3Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-198Coil C-3Install thermocouples (coil areas)YesOPEN
T-180Coil C-3Install strain gauges- fiber opticYesCLOSED8/13/2007
T-162Coil C-3Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-139Coil C-3Tie poloidal break shims & bolts electrically to the winding formNoOPEN
T-121Coil C-3Cover entire lead area with cover/boxNoOPEN
T-103Coil C-3Electrically tie the three jumper studs to the bottom jumperNoOPEN
T-069Coil C-3Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-005Coil C-3Over stock castings- use gauge block and grind clearances as necessary (Type C coils)YesOPEN
T-591Coil C-4Electrical test (7.5 kV) following winding form re-workYesOPEN
T-548Coil C-4Fabricate BushingsYesOPEN
T-511Coil C-4Install batt insulationYesOPEN
T-479Coil C-4Correct clamp interference (#63, 65, 69, 71)YesOPEN
T-460Coil C-4Secure terminal lug hardwareNoOPEN
T-450Coil C-4Add more fiducialsYesOPEN
T-431Coil C-4Check threads (run bolt through) on tapped holesYesCLOSED5/29/2007
T-413Coil C-4Check thread engagement on tapped holesYesCLOSED5/29/2007
T-395Coil C-4Grinding/milling to accommodate nut accessYesOPEN
T-377Coil C-4Add additional bolt holes (C-C)YesOPEN
T-359Coil C-4Grind overcastingYesOPEN
T-341Coil C-4Metrology (pre-measurement)YesOPEN
T-316Coil C-4Adjust cooling tubes for coil to coil fitOPEN
T-315Coil C-4Remove epoxy overflow fittingsYesOPEN
T-314Coil C-4Replace damaged co-wound loopYesCLOSED7/17/2007
T-313Coil C-4Complete electrical tests following VPIYesCLOSED12/12/2007
T-271Coil C-4Documentation package complete and ready for copyYesOPEN
T-253Coil C-4Mount final co-wound diagnostic box to castingYesCLOSED7/17/2007
T-235Coil C-4Lock all clamp hardware- weld locking wireYesCLOSED7/17/2007
T-217Coil C-4Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-199Coil C-4Install thermocouples (coil areas)YesOPEN
T-181Coil C-4Install strain gauges- fiber opticYesCLOSED8/13/2007
T-163Coil C-4Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-140Coil C-4Tie poloidal break shims & bolts electrically to the winding formNoOPEN
T-122Coil C-4Cover entire lead area with cover/boxNoOPEN
T-104Coil C-4Electrically tie the three jumper studs to the bottom jumperNoCLOSED6/15/2007
T-070Coil C-4Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-007Coil C-4Replace damaged co-wound loop side B [C4]YesCLOSED7/17/2007
T-592Coil C-5Electrical test (7.5 kV) following winding form re-workYesOPEN
T-549Coil C-5Fabricate BushingsYesCLOSED10/25/2007
T-512Coil C-5Install batt insulationYesOPEN
T-484Coil C-5Complete electrical tests following VPIYesCLOSED12/12/2007
T-480Coil C-5Correct clamp interference (#63, 65, 69, 71)YesCLOSED1/15/2008
T-461Coil C-5Secure terminal lug hardwareNoCLOSED1/15/2008
T-451Coil C-5Add more fiducialsYesCLOSED5/2/2007
T-432Coil C-5Check threads (run bolt through) on tapped holesYesCLOSED4/19/2007
T-414Coil C-5Check thread engagement on tapped holesYesCLOSED4/19/2007
T-396Coil C-5Grinding/milling to accommodate nut accessYesOPEN
T-378Coil C-5Add additional bolt holes (C-C)YesOPEN
T-360Coil C-5Grind overcastingYesOPEN
T-342Coil C-5Metrology (pre-measurement)YesCLOSED10/26/2007
T-319Coil C-5Adjust cooling tubes for coil to coil fitYesOPEN
T-318Coil C-5Remove epoxy overflow fittingsYesCLOSED4/2/2007
T-317Coil C-5Complete electrical tests following VPIYesCLOSED12/12/2007
T-272Coil C-5Documentation package complete and ready for copyYesOPEN
T-254Coil C-5Mount final co-wound diagnostic box to castingYesCLOSED4/10/2007
T-236Coil C-5Lock all clamp hardware- weld locking wireYesCLOSED4/10/2007
T-218Coil C-5Modify final coil clamps- permeability & fitup issuesYesCLOSED11/8/2007
T-200Coil C-5Install thermocouples (coil areas)YesQA CHECK
T-182Coil C-5Install strain gauges- fiber opticYesOPEN
T-164Coil C-5Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-141Coil C-5Tie poloidal break shims & bolts electrically to the winding formNoCLOSED10/18/2007
T-123Coil C-5Cover entire lead area with cover/boxNoOPEN
T-105Coil C-5Electrically tie the three jumper studs to the bottom jumperNoCLOSED1/15/2008
T-071Coil C-5Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-593Coil C-6Electrical test (7.5 kV) following winding form re-workYesOPEN
T-563Coil C-6Remove epoxy overflow fittingsYesOPEN
T-550Coil C-6Fabricate BushingsYesOPEN
T-513Coil C-6Install batt insulationYesOPEN
T-485Coil C-6Complete electrical tests following VPIYesOPEN
T-481Coil C-6Correct clamp interference (#63, 65, 69, 71)YesOPEN
T-462Coil C-6Secure terminal lug hardwareNoOPEN
T-452Coil C-6Add more fiducialsYesOPEN
T-433Coil C-6Check threads (run bolt through) on tapped holesYesOPEN
T-415Coil C-6Check thread engagement on tapped holesYesOPEN
T-397Coil C-6Grinding/milling to accommodate nut accessYesOPEN
T-379Coil C-6Add additional bolt holes (C-C)YesOPEN
T-361Coil C-6Grind overcastingYesOPEN
T-343Coil C-6Metrology (pre-measurement)YesOPEN
T-273Coil C-6Documentation package complete and ready for copyYesOPEN
T-255Coil C-6Mount final co-wound diagnostic box to castingYesOPEN
T-237Coil C-6Lock all clamp hardware- weld locking wireYesOPEN
T-219Coil C-6Modify final coil clamps- permeability & fitup issuesYesOPEN
T-201Coil C-6Install thermocouples (coil areas)YesOPEN
T-183Coil C-6Install strain gauges- fiber opticYesOPEN
T-165Coil C-6Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNoOPEN
T-142Coil C-6Tie poloidal break shims & bolts electrically to the winding formNoOPEN
T-124Coil C-6Cover entire lead area with cover/boxNoOPEN
T-106Coil C-6Electrically tie the three jumper studs to the bottom jumperNoOPEN
T-093Coil C-6Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateYesOPEN
T-085Coil C-6Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceYesOPEN
T-072Coil C-6Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]NoOPEN
T-059Coil C-6In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathNoOPEN
T-051Coil C-6Replace chill plates in lead and poloidal break areas with G-11 spacersYesOPEN
T-038Coil C-6Cut fingers of top chill platesYesOPEN
T-006Coil C-6Over stock castings- use gauge block and grind clearances as necessary (Type C coils)YesOPEN
T-575VVSA-1A1 to A2 gross fit testYesCLOSED12/3/2007
T-519VVSA-1C2 to C3 gross fit testYesCLOSED1/15/2008
T-518VVSA-1B2 to C2 gross fit testYesOPEN
T-517VVSA-1A2 to B2 gross fit testYesOPEN
T-516VVSA-1C1 to C5 gross fit testYesCLOSED10/26/2007
T-515VVSA-1B1 to C1 gross fit testYesCLOSED1/8/2008
T-514VVSA-1A1 to B1 gross fit testYesCLOSED7/26/2007
T-525VVSA-2C4 to C6 gross fit testYesOPEN
T-524VVSA-2B4 to C4 gross fit testYesOPEN
T-523VVSA-2A4 to B4 gross fit testYesOPEN
T-522VVSA-2A3 to A4 gross fit testYesOPEN
T-521VVSA-2B3 to C3 gross fit testYesOPEN
T-520VVSA-2A3 to B3 gross fit testYesOPEN
T-530VVSA-3B6 to C5 gross fit testYesOPEN
T-529VVSA-3A6 to B6 gross fit testYesOPEN
T-528VVSA-3A5 to A6 gross fit testYesOPEN
T-527VVSA-3B5 to C6 gross fit testYesOPEN
T-526VVSA-3A5 to B5 gross fit testYesOPEN
FileMaker Pro Version: 8.0v3
Build: 03-20-2006