Database: NCSX PUNCHLIST.fp7 |
Records: 593 |
Task No. | Item | Ref. | Description | Work Status | Update | FPA | Status |
T-079 | Coil B-1 | ECN 5140 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | Not Started | | No | OPEN |
T-131 | Coil B-1 | ECN 5140 | Cover entire lead area with cover/box | Not Started | | No | OPEN |
T-172 | Coil B-1 | | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | Not Started | | No | OPEN |
T-280 | Coil B-1 | | Documentation package complete and ready for copy | In-Progress | | Yes | OPEN |
T-502 | Coil B-1 | | Install batt insulation | Not Started | | Yes | OPEN |