Database: NCSX PUNCHLIST.fp7 |
Records: 593 |
Task No. | Item | Ref. | Description | Work Status | Update | FPA | Status |
T-080 | Coil B-2 | ECN5140 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | Not Started | | No | OPEN |
T-132 | Coil B-2 | ECN5140 | Cover entire lead area with cover/box | Not Started | | No | OPEN |
T-173 | Coil B-2 | | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | Not Started | | No | OPEN |
T-209 | Coil B-2 | | Install thermocouples (coil areas) | In-Progress | | Yes | OPEN |
T-281 | Coil B-2 | | Documentation package complete and ready for copy | In-Progress | | Yes | OPEN |
T-351 | Coil B-2 | | Grind overcasting | In-Progress | Grind additional areas noted in B1-C1 gross fit | Yes | OPEN |
T-503 | Coil B-2 | | Install batt insulation | Complete | | Yes | QA CHECK |
T-583 | Coil B-2 | | Electrical test (7.5 kV) following winding form re-work | Not Started | | Yes | OPEN |
FileMaker Pro Version: 8.0v3 |
Build: 03-20-2006 |