Database: NCSX PUNCHLIST.fp7
Records: 593
Task No.ItemRef.DescriptionWork StatusUpdateFPAStatus
T-082Coil B-4ECN 5140Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]Not StartedNoOPEN
T-134Coil B-4ECN 5140Cover entire lead area with cover/boxNot StartedNoOPEN
T-175Coil B-4Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNot StartedNoOPEN
T-211Coil B-4Install thermocouples (coil areas)CompleteYesQA CHECK
T-283Coil B-4Documentation package complete and ready for copyIn-ProgressYesOPEN
T-353Coil B-4Grind overcastingIn-ProgressGrind additional areas noted in B1-C1 gross fitYesOPEN
T-407Coil B-4Check thread engagement on tapped holesNot StartedYesOPEN
T-425Coil B-4Check threads (run bolt through) on tapped holesNot StartedYesOPEN
T-453Coil B-4NCR 3696Remove supplier's tooling ball insertsNot StartedYesOPEN
T-505Coil B-4Install batt insulationNot StartedYesOPEN
T-585Coil B-4Electrical test (7.5 kV) following winding form re-workNot StartedYesOPEN