Task No.ItemRef.DescriptionWork StatusUpdateFPAStatus
T-049Coil B-5ECN 5140Cut fingers of top chill platesIn-ProgressYesOPEN
T-057Coil B-5ECN 5140Replace chill plates in lead and poloidal break areas with G-11 spacersIn-ProgressYesOPEN
T-065Coil B-5ECN 5140In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathIn-ProgressNoOPEN
T-083Coil B-5ECN 5140Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]Not StartedNoOPEN
T-091Coil B-5ECN 5140Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceIn-ProgressYesOPEN
T-099Coil B-5ECN 5140Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateIn-ProgressYesOPEN
T-117Coil B-5ECN 5140Electrically tie the three jumper studs to the bottom jumperNot StartedNoOPEN
T-135Coil B-5ECN 5140Cover entire lead area with cover/boxNot StartedNoOPEN
T-153Coil B-5ECN 5140Tie poloidal break shims & bolts electrically to the winding formNot StartedRequires wire and weldingNoOPEN
T-176Coil B-5Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNot StartedNoOPEN
T-194Coil B-5Install strain gauges- fiber opticNot StartedNeed design/Materials - awaiting Oak Ridge to finalizeYesOPEN
T-212Coil B-5Install thermocouples (coil areas)Not StartedYesOPEN
T-230Coil B-5NCR 3634/3639Modify final coil clamps- permeability & fitup issuesNot StartedYesOPEN
T-248Coil B-5Lock all clamp hardware- weld locking wireIn-ProgressYesOPEN
T-266Coil B-5Mount final co-wound diagnostic box to castingIn-ProgressYesOPEN
T-284Coil B-5Documentation package complete and ready for copyIn-ProgressYesOPEN
T-336Coil B-5Metrology (pre-measurement)Not StartedYesOPEN
T-354Coil B-5Grind overcastingIn-ProgressGrind additional areas noted in B1-C1 gross fitYesOPEN
T-390Coil B-5Grinding/milling to accommodate nut accessIn-ProgressYesOPEN
T-408Coil B-5Check thread engagement on tapped holesNot StartedYesOPEN
T-426Coil B-5Check threads (run bolt through) on tapped holesNot StartedYesOPEN
T-434Coil B-5NCR 3700Remove supplier's tooling ball insertsNot StartedYesOPEN
T-445Coil B-5Not StartedAdd more fiducialsNot StartedWork Request submitted (N1150)/Inconel rod on orderYesOPEN
T-474Coil B-5Correct clamp interference (#60, 69)Not StartedYesOPEN
T-494Coil B-5Complete electrical tests following VPINot StartedYesOPEN
T-506Coil B-5Install batt insulationNot StartedYesOPEN
T-543Coil B-5Fabricate BushingsNot StartedYesOPEN
T-561Coil B-5Remove epoxy overflow fittingsNot StartedYesOPEN
T-571Coil B-5Secure terminal lug hardwareNot StartedNoOPEN
T-586Coil B-5Electrical test (7.5 kV) following winding form re-workNot StartedYesOPEN