Task No.ItemRef.DescriptionWork StatusUpdateFPAStatus
T-050Coil B-6ECN 5140Cut fingers of top chill platesIn-ProgressYesOPEN
T-058Coil B-6ECN 5140Replace chill plates in lead and poloidal break areas with G-11 spacersIn-ProgressYesOPEN
T-066Coil B-6ECN 5140In power bus tie in area- Install Kapton insulation over bolt to mitigate potentially short tracking pathIn-ProgressNoOPEN
T-084Coil B-6ECN 5140Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]Not StartedNoOPEN
T-092Coil B-6ECN 5140Install a Kapton or thin G-11 sheet underneath the jumper stack to increase the tracking distanceIn-ProgressYesOPEN
T-100Coil B-6ECN 5140Install insulating plugs at bottom of the hole in the G-11 base plate to reduce the risk of the studs penetrating the G-11 backing plateIn-ProgressYesOPEN
T-118Coil B-6ECN 5140Electrically tie the three jumper studs to the bottom jumperNot StartedNoOPEN
T-136Coil B-6ECN 5140Cover entire lead area with cover/boxNot StartedNoOPEN
T-177Coil B-6Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNot StartedNoOPEN
T-195Coil B-6Install strain gauges- fiber opticNot StartedNeed design/Materials - awaiting Oak Ridge to finalizeYesOPEN
T-213Coil B-6Install thermocouples (coil areas)Not StartedYesOPEN
T-231Coil B-6NCR 3634/3639Modify final coil clamps- permeability & fitup issuesNot StartedYesOPEN
T-249Coil B-6Lock all clamp hardware- weld locking wireIn-ProgressYesOPEN
T-267Coil B-6Mount final co-wound diagnostic box to castingIn-ProgressYesOPEN
T-285Coil B-6Documentation package complete and ready for copyIn-ProgressYesOPEN
T-337Coil B-6Metrology (pre-measurement)Not StartedYesOPEN
T-355Coil B-6Grind overcastingNot StartedGrind additional areas noted in B1-C1 gross fitYesOPEN
T-391Coil B-6Grinding/milling to accommodate nut accessIn-ProgressYesOPEN
T-409Coil B-6Check thread engagement on tapped holesNot StartedYesOPEN
T-427Coil B-6Check threads (run bolt through) on tapped holesNot StartedYesOPEN
T-475Coil B-6Correct clamp interference (#60, 69)Not StartedYesOPEN
T-495Coil B-6Complete electrical tests following VPINot StartedYesOPEN
T-507Coil B-6Install batt insulationNot StartedYesOPEN
T-544Coil B-6Fabricate BushingsIn-ProgressYesOPEN
T-562Coil B-6Remove epoxy overflow fittingsNot StartedYesOPEN
T-572Coil B-6Secure terminal lug hardwareNot StartedNoOPEN
T-587Coil B-6Electrical test (7.5 kV) following winding form re-workNot StartedYesOPEN