| Database: NCSX PUNCHLIST.fp7 |
| Records: 593 |
| Task No. | Item | Ref. | Description | Work Status | Update | FPA | Status |
| T-067 | Coil C-1 | ECN 5140 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | Not Started | | No | OPEN |
| T-119 | Coil C-1 | ECN 5140 | Cover entire lead area with cover/box | Not Started | | No | OPEN |
| T-160 | Coil C-1 | | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | Not Started | | No | OPEN |
| T-268 | Coil C-1 | | Documentation package complete and ready for copy | In-Progress | | Yes | OPEN |
| T-457 | Coil C-1 | | Secure terminal lug hardware | Not Started | | No | OPEN |
| T-508 | Coil C-1 | | Install batt insulation | Complete | | Yes | QA CHECK |
| T-588 | Coil C-1 | | Electrical test (7.5 kV) following winding form re-work | Not Started | | Yes | OPEN |