Database: NCSX PUNCHLIST.fp7
Records: 593
Task No.ItemRef.DescriptionWork StatusUpdateFPAStatus
T-067Coil C-1ECN 5140Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]Not StartedNoOPEN
T-119Coil C-1ECN 5140Cover entire lead area with cover/boxNot StartedNoOPEN
T-160Coil C-1Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNot StartedNoOPEN
T-268Coil C-1Documentation package complete and ready for copyIn-ProgressYesOPEN
T-457Coil C-1Secure terminal lug hardwareNot StartedNoOPEN
T-508Coil C-1Install batt insulationCompleteYesQA CHECK
T-588Coil C-1Electrical test (7.5 kV) following winding form re-workNot StartedYesOPEN