Database: NCSX PUNCHLIST.fp7 |
Records: 593 |
Task No. | Item | Ref. | Description | Work Status | Update | FPA | Status |
T-068 | Coil C-2 | ECN5140 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | Not Started | | No | OPEN |
T-120 | Coil C-2 | ECN5140 | Cover entire lead area with cover/box | Not Started | | No | OPEN |
T-161 | Coil C-2 | | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | Not Started | | No | OPEN |
T-197 | Coil C-2 | | Install thermocouples (coil areas) | In-Progress | | Yes | OPEN |
T-269 | Coil C-2 | | Documentation package complete and ready for copy | In-Progress | | Yes | OPEN |
T-323 | Coil C-2 | QA Action Ticket | Adjust cooling tubes for coil to coil fit | Not Started | | | OPEN |
T-324 | Coil C-2 | QA Action Ticket | Grind poloidal bk. winding clamp stud | Not Started | | | OPEN |
T-357 | Coil C-2 | | Grind overcasting | Not Started | Grind additional areas noted in B1-C1 gross fit | Yes | OPEN |
T-509 | Coil C-2 | | Install batt insulation | Not Started | | Yes | OPEN |
T-589 | Coil C-2 | | Electrical test (7.5 kV) following winding form re-work | Not Started | | Yes | OPEN |