Database: NCSX PUNCHLIST.fp7 |
Records: 593 |
Task No. | Item | Ref. | Description | Work Status | Update | FPA | Status |
T-005 | Coil C-3 | NCR 3643 | Over stock castings- use gauge block and grind clearances as necessary (Type C coils) | Not Started | To be completed at shop when cutting new bolt holes | Yes | OPEN |
T-069 | Coil C-3 | ECN 5140 | Install insulating washers on one side of the power bus connection to eliminate floating hardware [4] | Not Started | | No | OPEN |
T-103 | Coil C-3 | ECN 5140 | Electrically tie the three jumper studs to the bottom jumper | Not Started | | No | OPEN |
T-121 | Coil C-3 | ECN 5140 | Cover entire lead area with cover/box | Not Started | | No | OPEN |
T-139 | Coil C-3 | ECN 5140 | Tie poloidal break shims & bolts electrically to the winding form | Not Started | Requires wire and welding | No | OPEN |
T-162 | Coil C-3 | | Terminate cooling lines- braze fitting to tubes/ fill tube penetration holes | Not Started | | No | OPEN |
T-198 | Coil C-3 | | Install thermocouples (coil areas) | Not Started | | Yes | OPEN |
T-252 | Coil C-3 | | Mount final co-wound diagnostic box to casting | In-Progress | | Yes | OPEN |
T-270 | Coil C-3 | | Documentation package complete and ready for copy | In-Progress | | Yes | OPEN |
T-307 | Coil C-3 | QA Action Ticket | Adjust cooling tubes for coil to coil fit | Not Started | | | OPEN |
T-340 | Coil C-3 | | Metrology (pre-measurement) | Not Started | | Yes | OPEN |
T-358 | Coil C-3 | | Grind overcasting | In-Progress | Grind additional areas noted in B1-C1 gross fit | Yes | OPEN |
T-412 | Coil C-3 | | Check thread engagement on tapped holes | Not Started | | Yes | OPEN |
T-430 | Coil C-3 | | Check threads (run bolt through) on tapped holes | Not Started | | Yes | OPEN |
T-449 | Coil C-3 | Not Started | Add more fiducials | Not Started | | Yes | OPEN |
T-459 | Coil C-3 | | Secure terminal lug hardware | Not Started | Needs parts and welding | No | OPEN |
T-510 | Coil C-3 | | Install batt insulation | Not Started | | Yes | OPEN |
T-590 | Coil C-3 | | Electrical test (7.5 kV) following winding form re-work | Not Started | | Yes | OPEN |
FileMaker Pro Version: 8.0v3 |
Build: 03-20-2006 |