Database: NCSX PUNCHLIST.fp7
Records: 593
Task No.ItemRef.DescriptionWork StatusUpdateFPAStatus
T-070Coil C-4ECN 5140Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]Not StartedNoOPEN
T-122Coil C-4ECN 5140Cover entire lead area with cover/boxNot StartedNoOPEN
T-140Coil C-4ECN 5140Tie poloidal break shims & bolts electrically to the winding formNot StartedRequires wire and weldingNoOPEN
T-163Coil C-4Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNot StartedNoOPEN
T-199Coil C-4Install thermocouples (coil areas)Not StartedYesOPEN
T-271Coil C-4Documentation package complete and ready for copyIn-ProgressYesOPEN
T-315Coil C-4QA Action TicketRemove epoxy overflow fittingsNot StartedYesOPEN
T-316Coil C-4QA Action TicketAdjust cooling tubes for coil to coil fitNot StartedOPEN
T-341Coil C-4Metrology (pre-measurement)Not StartedYesOPEN
T-359Coil C-4Grind overcastingNot StartedGrind additional areas noted in B1-C1 gross fitYesOPEN
T-377Coil C-4Add additional bolt holes (C-C)Not StartedYesOPEN
T-395Coil C-4Grinding/milling to accommodate nut accessNot StartedYesOPEN
T-450Coil C-4Not StartedAdd more fiducialsNot StartedWork Request submitted (N1150)/Inconel rod on orderYesOPEN
T-460Coil C-4Secure terminal lug hardwareNot StartedNeeds parts and weldingNoOPEN
T-479Coil C-4Correct clamp interference (#63, 65, 69, 71)Not StartedYesOPEN
T-511Coil C-4Install batt insulationNot StartedYesOPEN
T-548Coil C-4Fabricate BushingsNot StartedYesOPEN
T-591Coil C-4Electrical test (7.5 kV) following winding form re-workNot StartedYesOPEN
FileMaker Pro Version: 8.0v3
Build: 03-20-2006