Database: NCSX PUNCHLIST.fp7
Records: 593
Task No.ItemRef.DescriptionWork StatusUpdateFPAStatus
T-071Coil C-5ECN 5140Install insulating washers on one side of the power bus connection to eliminate floating hardware [4]Not StartedNoOPEN
T-123Coil C-5ECN 5140Cover entire lead area with cover/boxIn-ProgressTemporary plastic box installedNoOPEN
T-164Coil C-5Terminate cooling lines- braze fitting to tubes/ fill tube penetration holesNot StartedNoOPEN
T-182Coil C-5Install strain gauges- fiber opticNot StartedNeed design/Materials - awaiting Oak Ridge to finalizeYesOPEN
T-200Coil C-5Install thermocouples (coil areas)CompleteYesQA CHECK
T-272Coil C-5Documentation package complete and ready for copyIn-ProgressYesOPEN
T-319Coil C-5QA Action TicketAdjust cooling tubes for coil to coil fitNot StartedYesOPEN
T-360Coil C-5Grind overcastingNot StartedGrind additional areas noted in B1-C1 gross fitYesOPEN
T-378Coil C-5Add additional bolt holes (C-C)Not StartedYesOPEN
T-396Coil C-5Grinding/milling to accommodate nut accessNot StartedYesOPEN
T-512Coil C-5Install batt insulationNot StartedYesOPEN
T-592Coil C-5Electrical test (7.5 kV) following winding form re-workNot StartedYesOPEN