Changing the meeting time to 3:30 to facilitate people making
Jim's 4:00 meeting.
2/27/07
VV:
Monday, moved VV1 to floor and VV3 on
stand.
Today we got 6 more loops installed on VV2 ~20
remaining.
MCWF:
Lift
coil and lowered onto flat flange.
It rested on the poloidal break, and two points near
the nose. Picture attached
We were able to run a 4-7 thousandths feeler completely
around the flange except for the 3 points touching.
Conclusion: the flange is fairly flat except for a few
arbitrary points.
lifted the B4 coil and rotated it to check fit to
wedge.
Flip wedge.
Put in work order for templates of each flange surface
entire area including from ID to OD and feet.
JOHN: TOMORROW (Wednesday 2/28 ):
Fit A1
to wedge. B1 is the first wound coil and is in the oven. Won't be ready
for a couple of weeks.
Fit B4
to A1 for gross check to determine gross interferences.
Wednesday/Thursday
Order
more tubing for tooling ball holders BUT buy the ID slightly undersize so we can
ream them to get a better fit.
UPCOMING (Thursday -
...)
Fit A1
to A2 to determine gross interferences. Thursday/Friday
Measure A1 and A2. Monday...
NEED:
DXF files of
flanges
Brown - Provide areas to scan "A" coils - COB
Thursday - 90%
COMPLETE
Ellis
- provide actual monuments and fiducials locations - COB
Thursday
Perform scans and install fiducials.
Friday
Brooks - provide
A1 - A2 actual fit up data - Monday
Perform alignment trials - Next
week
Thanks,
Mike
Viola, PPPL, (609) 243 3655
Today we held our first FPA daily coordination
meeting.
I promise it will be short 10-15
minutes.
1) Brief description of what was
accomplished that day
2) Brief description of the plan for the
following day - listing any required support
2/26/07
VV:
Today we got 5 more
loops installed
MCWF:
Measured B4 coil on
stand.
Learned that lower
flange fiducials are ~.190 inboard from actual.
Aligned to only one
of the 2 flanges "B" flange
"A" flange all out
~0.190" out.
As Steve pulled the
tooling ball out, the reading passed through 0.
Now have precise
alignment to upper half (~2-4 thousands)
Walking around the
part measuring everything on top flange.
Shot extra points
around the room to leap frog around part.
TOMORROW
(Tuesday 2/27):
Lift coil and lower
onto 3 points.
One near each leg
and one at the nose.
Remeasure upper
flange face to determine any sag.
UPCOMING
(Wednesday-...)
Fit B4 to A1 to
determine gross interferences. Wednesday/Thursday
Fit A1 to A2 to
determine gross interferences. Thursday/Friday
Measure A1 and A2.
Monday...
NEED:
Brown - Provide
areas to scan "A" coils - COB Thursday
Ellis - provide
actual monuments and fiducials locations - COB Thursday
Perform scans and install fiducials.
Friday
Brooks - provide A1 - A2 actual fit up data -
Monday
Perform alignment
trials - Next week
Thanks,
Mike
Viola, PPPL, (609) 243 3655