2/28/07
VV:
Today we
got 7 more loops
installed on VV2 ~14
remaining.
Expect to complete
Tuesday and will be out of work for VV FPA.
FPA computer has hard
drive problem.
Computer division
working on it.
Second laser tracker
would be good now – will be on VV3 for 2 weeks – competing with A1 and A2
scans
MCWF:
Fit A1 to wedge. Wedge
needs rework to accommodate A
wings.
Work order and wedge
delivered to shop.
JOHN: TOMORROW
(Thursday 3/1):
Continue working on
loops.
Retrieve computer and
begin VV3 scanning
UPCOMING
(Friday -
...)
Retrieve
wedge.
Fit B4 to A1 for gross
check to determine gross interferences. Wednesday/Thursday
Fit A1 to A2 to
determine gross interferences. Thursday/Friday
Measure A1 and A2.
Monday...
NEED:
Cooling tube
parts
Heater
tapes
Boxes and terminal
strips for diagnostic coils
Williamson – DXF files of flanges
Second Laser tracker –
will be on VV3 for 2 weeks – competing with A1 and A2
scans
Brown -
Provide areas to scan "A"
coils - COB Thursday - 90% COMPLETE
Ellis - provide actual
monuments and fiducials locations - COB Thursday
Perform scans and
install fiducials. Friday
Brooks - provide A1 -
A2 actual fit up data - Monday
Perform alignment
trials - Next week
Thanks,
Mike