From: Michael E. Viola
Sent: Wednesday, February 28, 2007 3:49 PM
To: Michael E. Viola; Wayne T. Reiersen; Thomas G. Brown; Steve Raftopoulos; Robert A. Ellis; Arthur W. Brooks; Lawrence E. Dudek; John W. Edwards
Cc: Ronald L. Strykowsky; Hutch Neilson; 'Cole, Michael'; Bob Simmons
Subject: FPA Daily Coordination meeting 2/28/07

2/28/07

VV:

Today we got 7 more loops installed on VV2 ~14 remaining.

Expect to complete Tuesday and will be out of work for VV FPA.

FPA computer has hard drive problem. 

Computer division working on it. 

Second laser tracker would be good now – will be on VV3 for 2 weeks – competing with A1 and A2 scans

 

MCWF:

Fit A1 to wedge. Wedge needs rework to accommodate A wings.

Work order and wedge delivered to shop.

 

JOHN: TOMORROW (Thursday 3/1):

Continue working on loops.

Retrieve computer and begin VV3 scanning

 

UPCOMING (Friday - ...)

Retrieve wedge.

Fit B4 to A1 for gross check to determine gross interferences. Wednesday/Thursday

Fit A1 to A2 to determine gross interferences. Thursday/Friday

Measure A1 and A2. Monday...

 

NEED:

Cooling tube parts

Heater tapes

Boxes and terminal strips for diagnostic coils

Williamson – DXF files of flanges

Second Laser tracker – will be on VV3 for 2 weeks – competing with A1 and A2 scans

 

Brown - Provide areas to scan "A" coils - COB Thursday - 90% COMPLETE

Ellis - provide actual monuments and fiducials locations - COB Thursday

Perform scans and install fiducials. Friday

Brooks - provide A1 - A2 actual fit up data - Monday

Perform alignment trials - Next week

 

Thanks,

Mike Viola, PPPL, (609) 243 3655