3/26/07
VV:
Covered heater tapes
MCWF:
Mike Duco is out today.
Ed Bush continued measuring A2.
JOHN: Tuesday 3/26:
Complete scanning A2 and provide data to Art Brooks.
Brooks - provide A1 - A2 actual fit up data
Brown - provide shim thicknesses ASAP.
Please measure length of groove in A1 A side for George.
UPCOMING
Align A1 to A2
NEEDS:
How is the heater tape leads and thermocouple leads routed through the horse collar? - George to Paul to update 009 drawing
Brooks - provide A1 - A2 actual fit up data – Thursday REALLY!!
Could use diagnostic loop junctions boxes.
George is getting the terminal strips ordered
Williamson – DXF files of flanges - Have "A" need others
Thanks,
Mike Viola, PPPL, (609) 243 3655