VV:
Exchanged VV! for VV3
Installed 3 of the 4 voltage loops on VV1.
MCWF:
Began Ellis measurement plan A1 on wedge - B side down
Difficulty locking in - out 0.020"
Viola completed the spreadsheet of flange bolts (attached)
Will discuss at Monday's meeting.
JOHN: Monday 3/12 :
Install 8 more square tubes to see if sagging is an issue.
Remeasure coil
Flip A1
Continue Ellis measurement plan .
UPCOMING
Continue Ellis measurement plan .Stand selected coil on feet (vertical)
Weld on external fiducials
Measure fiducials and flanges and tooling balls with Leica.
Lay coil flat on wedge and remeasure fiducials and flanges and tooling balls.
Perform scans and install fiducials. Monday
Pull tension on the two threaded insert on A1 and 8 on B2 (B4?) and then repair
NEEDS:
Cooling tube parts – starting to flow in from shop - however
Heater tapes – Briskheat reports will be a 1 week delay Monday March 12 due to vacation
Strykowsky – Boxes and terminal strips for diagnostic coils – George received go ahead from project
Williamson – DXF files of flanges - Have "A" need others
Ellis - provide actual monuments and fiducials locations - COB Thursday
Brooks - provide A1 - A2 actual fit up data - Monday
Perform alignment trials - Next week (Crane utilization conflicts with coil winding.)
Thanks,
Mike Viola, PPPL, (609) 243 3655