3/8/07

VV:

Exchanged VV! for VV3

Installed 3 of the 4 voltage loops on VV1.

 

MCWF:

Began Ellis measurement plan A1 on wedge - B side down   

Difficulty locking in - out 0.020" 

Viola completed the spreadsheet of flange bolts (attached) 

     Will discuss at Monday's meeting.

 

JOHN:  Monday 3/12 :

Install 8 more square tubes to see if sagging is an issue.

Remeasure coil

Flip A1

Continue Ellis measurement plan .

 

UPCOMING

Continue Ellis measurement plan .

Stand selected coil on feet (vertical)

Weld on external fiducials

Measure fiducials and flanges and tooling balls with Leica.

Lay coil flat on wedge and remeasure fiducials and flanges and tooling balls.

Perform scans and install fiducials.  Monday  

Pull tension on the two threaded insert on A1 and 8 on B2 (B4?) and then repair

 

NEEDS:

Cooling tube parts –  starting to flow in from shop  - however 

Heater tapes  – Briskheat reports will be a 1 week delay Monday March 12 due to vacation 

Strykowsky – Boxes and terminal strips for diagnostic coils – George received go ahead from project 

Williamson – DXF files of flanges  - Have "A" need others

Ellis - provide actual monuments and fiducials locations - COB Thursday 

Brooks - provide A1 - A2 actual fit up data - Monday  

Perform alignment trials - Next week (Crane utilization conflicts with coil winding.)

 