John see A_A coil at bottom
for tomorrow
NEEDS:
FPA
documentation needs for Station 2 have been placed on hold until the design is
finalized.
Need
to Flip B1 toclean the epoxy flowed over the B side flange and poloidal
break.
Thursday: 5/17/07
Tracker still
stable.
Leica is
back
VV:
64 of
64 heating cooling lines installed on
VV2
About 2 days remain of
thermocouples and final tightening
Welder head
still broken. 2 weeks for evaluation.
Hope is to switch VV3
for VV1 then move on to scanning
VV3
MCWF:
Continued
A1 A2 fitup.
Was scanned then
torqued.
Scanned and
Files to follow
soon
Torque to 30 ft-lbs.
100% of the 75%
METROLOGY:
Measured
B-1
B-1 needs to be flipped
to measure fiducials including the external
monuments
5/18:
VV:
Please consider putting
VV3 on the stand for measurement.
The
maximum tension during any of the coil testing is 55,000 lbs.
Which
is equivalent to 30 ft-lbs on the supernut
jackbolts.
Where
we have through bolts, we can go to the full 75,000 lbs
tension
Which
is equivalent to 40 ft-lbs on the supernut
jackbolts.
MCWF:
Larry would like to add
a step:
Measure after torque
condition and replace the 5 thru bolts corner
torque thru bolts
to 75% and then replace
retorque
to100%
METROLOGY:
Continue measuring
B-1.
Please move B-1 to the
new wedge and measure B-1 on the new wedge with current side
up.
Then flip and remeasure
Crane will be
unavailable on Friday
Thanks,
Mike
Viola, PPPL, (609) 243 3655
1 0.509
2 0.509
3 0.509
4 0.510
5 0.507
6 0.503
7 0.500
8 0.502
9 0.505
10 0.525
11 0.525
12 0.516
13 0.513
14 0.509
15 0.505
16 0.506
17 0.497
18 0.497
19 0.496
20 0.498