From: Michael E. Viola
Sent: Friday, March 02, 2007 3:57 PM
To: Michael E. Viola; Wayne T. Reiersen; Thomas G. Brown; Steve Raftopoulos; Robert A. Ellis; Arthur W. Brooks; Lawrence E. Dudek; John W. Edwards
Cc: Ronald L. Strykowsky; Hutch Neilson; 'Cole, Michael'; Bob Simmons
Subject: RE: FPA Daily Coordination meeting 3/2/07

Attachments: IMG_0267.jpg; IMG_0268.jpg; IMG_0269.jpg; IMG_0282.jpg; IMG_0284.jpg; IMG_0288.jpg; IMG_0290.jpg; IMG_0296.jpg; IMG_0297.jpg
3/2/07

VV:

Today we got 7 more loops installed on VV2 ~ 2  remaining. 

Continued VV3 scanning

 

MCWF:

Fit B4 to A1 for gross check to determine gross interferences.  

Found 3 hard interferences (see pictures) 

 

JOHN:  Monday (Friday 3/5 ):

Finish working on loops. 

Continue VV3 scanning

Fit A1 to wedge.

 

UPCOMING ( Monday  - ...)

Rework wedge to accommodate "B" side of the A type.

Fit A to Ato determine gross interferences.

Measure A1 and A2.  Tuesday ...

 

NEEDS:

Metrology: ARLENE needs the req. - resolved

Cooling tube parts –  starting to flow in from shop 

Heater tapes  – Briskheat reports will be a 1 week delay of investigation due to vacation 

Strykowsky – Boxes and terminal strips for diagnostic coils – George received go ahead from project 

Williamson – DXF files of flanges  - Have "A" need others

Ellis - provide actual monuments and fiducials locations - COB Thursday 

Perform scans and install fiducials.  Monday 

Brooks - provide A1 - A2 actual fit up data - Monday  

Perform alignment trials - Next week (Crane utilization conflicts with coil winding.)

 

Thanks,

Mike Viola, PPPL, (609) 243 3655