VV:
Today we got 7 more loops installed on VV2 ~ 2 remaining.
Continued VV3 scanning
MCWF:
Fit B4 to A1 for gross check to determine gross interferences.
Found 3 hard interferences (see pictures)
JOHN: Monday (Friday 3/5 ):
Finish working on loops.
Continue VV3 scanning
Fit A1 to wedge.
UPCOMING ( Monday - ...)
Rework wedge to accommodate "B" side of the A type.
Fit A2 to A1 to determine gross interferences.
Measure A1 and A2. Tuesday ...
NEEDS:
Metrology: ARLENE needs the req. - resolved
Cooling tube parts – starting to flow in from shop
Heater tapes – Briskheat reports will be a 1 week delay of investigation due to vacation
Strykowsky – Boxes and terminal strips for diagnostic coils – George received go ahead from project
Williamson – DXF files of flanges - Have "A" need others
Ellis - provide actual monuments and fiducials locations - COB Thursday
Perform scans and install fiducials. Monday
Brooks - provide A1 - A2 actual fit up data - Monday
Perform alignment trials - Next week (Crane utilization conflicts with coil winding.)
Thanks,
Mike Viola, PPPL, (609) 243 3655