From:
Hutch Neilson
Sent: Thursday, February 14, 2008 6:02 PM
To:
Phil Heitzenroeder; Lawrence E. Dudek; Alfred von Halle; Mike Cole; Michael E.
Viola; Thomas G. Brown; Ronald L. Strykowsky; Bob Simmons; Brentley C. Stratton;
Erik D. Perry; Steve Raftopoulos; Subrahmanya Ramakrishnan; Michael R. Kalish;
James H. Chrzanowski; Paul Goranson; Paul Sichta
Cc: Jeffrey Harris;
Mike Williams; Don Rej
Subject: NCSX Interfaces, revised
Folks,
I am re-issuing this list with recent information.
Tom, I have tried to address your ownership questions as much as
possible.
This is my understanding of the responsibilities for
services that connect to the stellarator core:
Diagnostic cables: B. Stratton (WBS 3)
Thermocouple leads: E. Perry (WBS 7)
Heater tape leads: E. Perry (WBS 7)
Strain gauge leads: E. Perry (WBS 7)
Cryogenic lines: S. Raftopoulos (WBS 62)
Coil electrical leads: S. Ramakrishnan (WBS 4). Is this correct, or
is there an intermediate cable run between Raki and the machine that is owned by
someone else?
Coil voltage taps to measure coil resistance: S.
Ramakrishnan (WBS 4)
Grounding cables: S. Ramakrishnan (WBS 4)
Vessel heating and cooling lines: M. Kalish (WBS 64)
Cryostat circulation system: S. Raftopoulos (WBS
17)
150 C Bakeout System: M. Kalish (WBS
64)
Port heater tape system: P. Goranson (WBS
12)
Coil services thermal transition box: P. Goranson
(WBS 16)
Final I&C connections outside cryostat:
Tom or Erik, what is this and what is the issue?
Please let me know if there are corrections or further
questions.
Thanks.
Hutch