4
October, 2000
FROM: C NEUMEYER
SUBJECT: OPTIONS FOR NCSX POWER
SUPPLY SYSTEM
This memo presents some thoughts
on options for implementation of the NCSX power supply system. I think that we
should call a meeting including all of the electric power engineers here at
PPPL, along with interested NCSX parties, to discuss. Then after refinement,
and maybe with the development of some cost information, the choices should be
presented to lab management.
1) D-site
Power Supply (PS) Units are 12-pulse rectifiers consisting of two 6-pulse Power
Supply Sections (PSS) each pulse rated 1kV/24kA-6sec, once every 300 sec., and
continuous rated at +/-1kV/3.25kA. In some cases we have operated up to 30kA
with reduced pulse length. So each PS is pulse rated ≈ 2*24 = 48MVA, and
continuous rated ≈ 2*3.25 = 6.5MVA. Dimensions of a PS unit are
approx. 12’ wide x 12’ tall x 4’ deep per PS, not counting the cable throat in
the rear in which the transformer-to-rectifier cables are routed, along with
the ACCTs.
2) Each
PS is fed by a single three winding transformer (XFMR), oil filled and
installed outdoors.
3) The
PSS are fully insulated from one another, but subject to a common firing
generator/fault detector unit such that they operate in identical modes at
identical firing angles. However, control modifications would permit
independent control of the two PSS.
4) The
PSS are 2-quadrant, unipolar current, meaning +/- V but +I only. For bipolar
current, need to connect pairs of PSS in anti-parallel.
5) Equivalent
internal impedance of a PSS is of order 13.3mΩ, meaning that a 400V drop
will occur at 30kA.
6) There
are 37 fully rated PS, hence 74 fully rated PSS. There are two additional PS
which were used for the TFTR HF and VC systems but these are partially rated
and use smaller indoor dry type transformers, which are trapped in the building
by the other equipment.
7) Each
PSS consists of six parallel 6-pulse rectifier modules, and two parallel bypass
modules. For an NCSX pulse with t ≤ 3 seconds, only 1/2 of the
modules would be required. Furthermore, the bypass modules are probably not
required for NCSX.
8) Based
on certain assumed rates of inflation the cost of each XFMR in Y2K $ would be
$266K, and each PS would be $344K, total $610K per PS/XFMR unit. This amounts
to $12/KVA pulsed, $94/KVA continuous.
9) NSTX
requires a minimum of 21 of the 37 fully rated PS, based on the present
configuration, with the further assumption that the presently available on-line
spares would be sacrificed to NCSX. This leaves 16 PS units for NCSX, total 32
PSS (see list which follows).
10) The PS
units in the east-west wing of the FCPC building, formerly the TFTR TF power
supplies, are presently used by the NSTX TF system and OH system. Because these
units were connected in four parallel series strings, and because of the high
door located at the end of the aisle, these 12 PS units could be disconnected
with relative ease and removed.
11) The PS
units in the north-south wing of the FCPC building, formerly the TFTR PF power
supplies, are presently used by the NSTX PF and CHI systems. These units are
interconnected with each other and with other specialized components in such a
way that significant re-cabling would be required to separate them from the
NSTX circuits. Also, there is no simple way to physically remove them from the
building. However, their power modules, Master Gate Drive (MGD) systems, and
their XFMRs are modular and could be easily removed and relocated. In this case
new frames, with suitable AC and DC bus systems, cooling water systems, and
local control systems would have to be constructed to service the relocated
modules.
12) While the
PS power components are still in good condition and good working order, the control
systems are obsolete and showing serious signs of wear and tear. These facts,
combined with the likely need for NCSX to exercise controls over the individual
PSS rather than the pairs which make up each PS, suggests that control
modernization will be required in any case. One option to consider in this
regard would be to move toward the generation of firing pulses direct at the
central control computer to be transmitted digitally and at the last step,
optically, to the distributed MGD systems.
This would significantly reduce the parts count in the local controls,
and could reduce the cost and enhance the reliability of the final system.
13) The levels
of power under discussion exceed the capability of the present PPPL connection
to the 138kV grid. Therefore one MG system will be required. At present, only
one of the two MG systems is in use.
Therefore either the MG now operating would be time shared between NCSX
and NSTX, or the second MG set would be restored to service just for NCSX.
However, the latter approach would require that the 13.8kV feeder configuration
be re-arranged and segregated into two groups such that the NSTX feeders
connected to one MG output bus and the NCSX feeders to the other one.
14) To
implement a direct connection of 13.8kV MG power from D-site to C-site would
require that either iso-phase bus be extended from D-site to C-site, or
pyrobreakers be installed to limit the very high fault power available from the
MG. This approach is not practical. A better approach is to take the individual13.8kV
feeder output of the variable frequency switchgear, which is current limited
and protected, and extend it to C-site. In this case it may be desirable to add
an additional switchgear line-up at C-site, in series with the D-site
switchgear, for the purposes of providing an isolating safety break locally.
15) Power could
be transmitted in DC form from the rectifier outputs at D-site to the loads at
C-site. This would not impose an intolerable voltage drop or power loss (e.g.
the distance may not be that much greater than already is the case on NSTX).
16) The C-site
MG sets consist of three rotating shaft line-ups, each consisting of a motor,
flywheel, and four DC generators (total 12 generators). The generators were built
by Allis-Chalmers and first operated in 1960. The generators are separately
excited DC generators. The motors are wound rotor induction motors with speed
control by liquid rheostat. The exciters are cascade DC generators. Main
specifications are given in the following table.
C-site MG Specifications
(per shaft or per generator as applicable)
Parameter |
Value |
Units |
Motor Power |
7000 |
Hp |
Flywheel Weight |
96 |
tons |
Maximum Speed |
355 |
rpm |
Minimum Speed |
284 |
rpm |
Deliverable Energy |
137MJ |
MJoule |
Generator Maximum Voltage |
850 |
V |
Generator Maximum Voltage Derivative |
1.0 |
kV/sec |
Generator Continuous Ampacity |
5075 |
amp |
Generator Peak Pulse Current |
22.3 |
kA |
Generator Peak Pulse Power |
16.67 |
MW |
Generator Peak Pulse ESW |
2.0 |
sec |
Generator Peak Pulse Duty Cycle |
5.15 |
% |
Generator Armature Time Constant |
0.0165 |
sec |
Generator Field Time Constant |
1.85 |
sec |
Flat Top Current Regulation |
+/-1.0 |
% |
Comparing one of the twelve C-site generators to one of the
D-site PSS, the power level is 78%, and (assuming 1/3 of the shaft energy per
generator, and that the D-site PSS runs for 6 seconds at full rating and 80%
p.f.) 40% of the energy. Controllability is relatively poor. Ripple is
relatively good.
Implementation
Options
Nine implementation options are presented on the attached spreadsheet. The following is a discussion of same.
The 12 PS units and their transformers not required by NSTX in the east-west TF wing of FCPC would be relocated to C-site. Relatively simple modifications would be made to the DC cabling in FCPC to accommodate the removal. However, the 24 PSS would not be sufficient for NCSX. To cover the shortfall, the C-site MG sets could be brought into service.
Option 2
The 12 units mentioned in option 1, along with 4 additional PS/XFMR units from the FCPC north-south PF wing, not required for NSTX, would be relocated to C-site. The DC cabling in the FCPC PF wing would be modified to accommodate the change. The PS units to be moved would have to be completely disassembled since the frames are trapped in place. Then, either new frames would be built at C-site, or the existing frames would be cut apart and re-welded at C-site. This scheme would make available up to 32PSS, all identical to the existing PS configuration.
Option 3
The 12 units mentioned in option 1 would be relocated as per option 1. In addition the power modules, MGDs, and XFMRs would be relocated to C-site and new frames, AC/DC bus bar, water distribution, and local control systems would be built to form new PS units. The old frames, etc., would be left at D-site, and no DC cable changes would be required at D-site on the NSTX systems. This scheme would make available up to 32 PSS, 12 of the existing configuration, and 4 with the new assembly and accessories. The D-site system could be restored in necessary in the future by returning the XFMRs, power modules, and MGDs.
Option 4
Taking from all 16 of the PS units not required by NSTX, the power modules, MGDs, and XFMRs would be relocated to C-site and new frames, AC/DC bus bar, water distribution, and local control systems would be built to form new PS units. The old frames, etc., would be left at D-site, and no DC cable changes would be required at D-site on the NSTX systems. This scheme would make available up to 32 PSS, all of the new configuration. The D-site system could be restored in necessary in the future by returning the XFMRs, power modules, and MGDs.
Option 5
This is the same as option 4 except that new XFMRs would be used, and the D-site XFMRs would be left behind. Because NCSX requires pulse lengths of ≤ 3 seconds, it would be possible to realize up to 64PSS using the existing power modules.
DC cabling at FCPC would be
completely re-configured such that the outputs of the PSS were available for a
variety of connections in a patch-panel type of scheme. This might be
accomplished by adding penetrations between the 1st and 2nd
floors of FCPC, removing the offices located there, and installing suitable
cable/bus bar/bus link/disconnect switch systems. In this case all 74PSS would
be available to NSTX or NCSX, but not at the same time. The system would be
designed to allow switchover on the time scale of one week. NCSX would be
located at C-site, and the power would be shipped from D-to-C-site in DC form.
Current measurement and safety disconnect/grounding switches would probably be
located at D-site. And shared by NSTX and NCSX.
Same as Option 6 except NCSX
installed at D-site to eliminate high current DC transmission from D-to-C-site.
DC cabling at FCPC would be
significantly re-configured such that the outputs of the PSS for NSTX and those
for NCSX were fully segregated. This might require the addition of penetrations
between the 1st and 2nd floors of FCPC, and the removal
of the offices located there, to facilitate the installation of suitable
cable/bus bar/bus link/disconnect switch systems. In this case the 32PSS not
required by NSTX would be available to NCSX. The power would be shipped from
D-to-C-site in DC form. Current measurement and safety disconnect/grounding
switches would probably be located at C-site.
Same as Option 6 except NCSX
installed at D-site to eliminate high current DC transmission from D-to-C-site.
Cc:
R Hatcher
P Heitzenroeder
S Ramakrishnan
W Reiersen
J Schmidt
A Von Halle
M Williams