NCSX Memorandum
To: T. Brown, A. Brooks, H-M. Fan, B. Nelson, D. Williamson, M.
Cole, P. Goranson, R. Hatcher, C. Neumeyer, L. Dudek, P. Heitzenroeder, R.
Ramakrishnan, J. Chrzanowski, L. Dudek, A. Klink, H. Kugel
CC: J. Schmidt, H. Neilson, J. Lyon, S. Hirshman, M. Zarnstorff,
A. Reiman. L. Berry, D. Strickler, R. Simmons
From: W. Reiersen
Date: 1/18/2001
Re: Minutes of 1/17 Engineering telecon
An
engineering telecon was held on January 17.
The objective of the meeting was to leave with a clear understanding of
what work and deliverables are required to be completed in the next six weeks.
Phil
Heitzenroeder started the meeting by reporting on some design features that
appear desirable for assembly. He would
like to pre-assemble the stellarator core in thirds, if possible, prior to
bringing the sub-assemblies into the test cell for final assembly. The best place for pre-assembly would be the
empty TFTR test cell. Two concerns with
assembling the stellarator core in thirds are size (can we fit it through the
door into the NCSX test cell?) and weight (can we lift one third of the
stellarator core with an upgraded overhead crane?). Heitzenroeder argued for a bolted joint on the v=0.5 plane for
final assembly. With a 150C bakeout (assuming a 350C stand-alone liner), the
bolted joint could use double Viton
seals with a pumped inter-space. The
bolts would be tightened from the inside of the vacuum vessel. This should
create a reliable joint and avoid problems associated with welding (weld distortion
and very tight space) during final assembly. This would allow many of the
in-vessel components to be installed prior to final assembly and greatly
expedite the assembly process. Another
advantage of the bolted joint would be that the machine would be disassemble-able. This could be a significant advantage in the
event that a major failure or reconfiguration was required. The main concern appeared to be the extra
space required for the bolted joint.
The
three (one-third) machine sectors would be brought together by moving them
radially inward. Nelson indicated that
it might be necessary to bring the three sectors together simultaneously to
avoid interferences. Brown will develop
a concept for the base assembly that is consistent with this assembly approach.
The
next Engineering telecon will be held next Wednesday, January 17, at
1:30pm. Please provide the following
information in advance of the meeting:
Assess feasibility of bringing in one-third of
the stellarator core into the NCSX test cell and lifting it with an overhead
crane (Chrzanowski/ORNL)
Provide comparative assessment of bolted v.
welded joint for final assembly, recommendation for PVR (ORNL)
NB access at the reduced size (Cole)
Possibilities for beam scraping to reduce
horizontal width requirements (Kugel)
Prospects for manned access on boom mounted
creeper through port adjacent to NB port (Cole)
Why do we have fully potted coils and what are
the associated DT (J2t) limits
(Nelson)
Further thoughts on the free-standing,
bakeable liner including cost impact, selection of VV material (Nelson)
Assess technical feasibility of mounting trim
coils on inside of 150C VV (Nelson)
Impacts of eliminating PF4 (Reiersen, Cole)
Selection of winding cavity design – I-beam?
T-section? L-section? (Nelson)
Assess technical feasibility and cost
implications of using cast aluminum instead of SS (Nelson)
What do we think trim coils will look like
(Brooks)
Cost impact of reducing the number of NB in TPC
from 4 to 2 (Kugel)
Cost impact of reducing the number of circuits
in Day One configuration from 10 to 6 (Neumeyer)
Impacts of not disassembling PBX,
recommendation (Chrzanowski)
Current tally of costs requested by Director’s
Office (Simmons)
1.
Previous baseline estimate and contingency used in the
presentation to FESAC
2.
Present estimate for 1.7m option
3.
Present estimate for 1.4m option
4.
Actual
NSTX costs (mapped into NCSX WBS as closely as possible)