NCSX Memorandum
To: T. Brown, A. Brooks, H-M. Fan, B. Nelson, D. Williamson, M.
Cole, P. Goranson, R. Hatcher, C. Neumeyer, L. Dudek, P. Heitzenroeder, R.
Ramakrishnan, J. Chrzanowski, L. Dudek, A. Klink, H. Kugel
CC: J. Schmidt, H. Neilson, J. Lyon, S. Hirshman, M. Zarnstorff,
A. Reiman. L. Berry, D. Strickler, R. Simmons
From: W. Reiersen
Date: 1/18/2001
Re: Minutes of 1/17 Engineering telecon
An
engineering telecon was held on January 17.
The objective of the meeting was to leave with a clear understanding of
what work and deliverables are required to be completed in the next six weeks.
Phil
Heitzenroeder started the meeting by reporting on some design features that
appear desirable for assembly. He would
like to pre-assemble the stellarator core in thirds, if possible, prior to
bringing the sub-assemblies into the test cell for final assembly. The best place for pre-assembly would be the
empty TFTR test cell. Two concerns with
assembling the stellarator core in thirds are size (can we fit it through the
door into the NCSX test cell?) and weight (can we lift one third of the
stellarator core with an upgraded overhead crane?). Heitzenroeder argued for a bolted joint on the v=0.5 plane for
final assembly. With a 150C
bakeout (assuming a 350C stand-alone
liner), the bolted joint could use double Viton seals with a pumped
inter-space. The bolts would be
tightened from the inside of the vacuum vessel. This should create a reliable
joint and avoid problems associated with welding (weld distortion and very
tight space) during final assembly. This would allow many of the in-vessel
components to be installed prior to final assembly and greatly expedite the
assembly process. Another advantage of
the bolted joint would be that the machine would be disassemble-able. This could be a significant advantage in the
event that a major failure or reconfiguration was required. The main concerns appeared to be the extra
space and complexity required for the bolted joint.
The
three (one-third) machine sectors would be brought together by moving them
radially inward. Nelson indicated that
it might be necessary to bring the three sectors together simultaneously to
avoid interferences. Brown will develop
a concept for the base assembly that is consistent with this assembly approach.
Cole discussed NB access in the reduced size
machine. The reduced size machine
presented by Cole was reduced by a factor of 0.80 from the previous (1.7m)
design. The reference size is 0.82
times the previous design. Cole
indicated that he would update the model accordingly. The model that Cole presented had the beam well aimed at the
plasma. The beam was almost entirely
within the plasma except at a few isolated locations. However, it is plausible that the heat loads on the first wall
might be easily tolerated due to the fact that the beam was emerging from the
plasma and that only the fringes of the beam would infringe on the first wall
and at a very slight angle of incidence.
It is also conceivable that the first wall could be moved a bit further
away to avoid this interference altogether.
We agreed that this probably did not present a feasibility problem and
would pursue it in more detail after the PVR.
The outboard legs of the modular coils on the v=0 symmetry plane and of
the modular coils adjacent to the coils on the v=0 symmetry plane were a
greater concern (as seen in the figure below).
The
modular coils, photographically shrunk from the 1017 modular coil design,
clearly encroach on the vacuum vessel. Ditto
for the TF coils, which might pose an even more severe constraint. We should try to solve the NB access problem
by moving the outer legs of the modular and TF coils to avoid interference with
the VV and drift ducts. If this is not
possible, then we might have to make the case that we need to go to 18 coils
after the PVR.
Nelson provided a nice comparison of the
build elements for the previous and new reduced size designs (as shown in the
figure below).
In
the layout above, the thickness of the SOL and VV/FW envelope was held fixed,
which is a reasonable assumption. This
means a disproportionate reduction in the size of the winding packs for the
modular coils needs to be made. The
current machine parameters were based on a photographic reduction in the
machine size. Folding these fixed
build elements into the calculations will increase the current density and may
limit the field that can be attained with a 0.2s flattop. ORNL should define the radial build for the reduced size machine
and the new winding pack dimensions ASAP.
Reiersen should recalculate the performance parameters upon receiving
the new coil dimensions.
Nelson
also provided an update on the costs
based on his spreadsheet calculations for the reduced size device. The cost of the stellarator core (WBS 1)
came down $8.3M from the 1.7m device.
The data Nelson provided suggested that further cost reductions are
required to meet our $55M bogey. Nelson
and Heitzenroeder discussed their plans to get input on costs from
vendors. ORNL is preparing a technical
data package for the reduced size machine.
They expect to be finished this week.
ORNL will contact the group at Y12 for input on machining costs. ORNL will contact Southern Centrifugal and
Rondelet(?) for input on casting costs for coil structures. PPPL will contact US Bronze for input on
casting costs for coil structures and for casting costs and feasibility for the
vacuum vessel. PPPL will contact
Everson for input on winding costs. PPPL will contact Kharkov for input on vacuum vessel costs and
fabrication processes. Simmons noted
that the contract with Kharkov has not been signed so it is not clear whether
we will be successful in getting input from them for the PVR. Input is expected back the week of February
7. A list of upcoming cost and
schedule reviews has been posted on the Web. WBS 1 costs based on vendor inputs are scheduled for review
February 7.
Brown prepared a presentation showing an
alternate design concept. ORNL show
review the concept and determine next steps.
Brooks provided a very informative review of the
progress that has been made in trim coil design. He showed that the critical locations are near the inboard and
outboard midplanes at the v=0 (banana-shaped) cross section. This is where the coils are physically
closest to the resonant surfaces. It
also suggests that the proximity of the coils to the plasma will be a strong
factor in determining the amp-turn requirements for the coils. We need to show for the PVR that there
exists a plausible design solution for trim coils. After much discussion, it was decided that Brooks would pursue
the trim coil design on a surface offset 5cm behind the nominal first wall
surface. The nominal first wall surface
is located 2cm off the reference plasma boundary on the inboard side and 10cm
off on the outboard side. It appeared
that we could get by with the fewest number of coils and electrical circuits by
designing a set of picture frame coils for the m=5 resonance and a separate set
for the m=6 resonance. This would
hopefully result in the lowest cost solution.
Brooks will define the geometry for these coils and pass them to
ORNL. ORNL will resolve interferences
with the neutral beams and other immutable features and pass back a revised
geometry to Brooks to recalculate currents and effectiveness. Once the coil geometry and currents have
been set, a design concept for the trim coils will be developed. Hopefully, they can be conduction cooled to
an actively cooled support structure (like the vacuum vessel on the inboard
side). Coil current and voltage
requirements will be generated for the multi-turn coils and passed on to the
electrical power folks for power supply design and costing.
Reiersen closed the meeting with a review of
upcoming milestones and deliverables. We are on an
exceedingly tight schedule preparing for the PVR. Please pay strict attention to the upcoming milestones and
deliverables so we can stay on track for our PVR preparations.
The
next Engineering telecon will be held next Wednesday, January 24, at
1:30pm. Please provide the following
information in advance of the meeting:
Assess feasibility of bringing in one-third of
the stellarator core into the NCSX test cell and lifting it with an overhead
crane (Chrzanowski/ORNL)
Provide comparative assessment of bolted v.
welded joint for final assembly, recommendation for PVR (ORNL)
Define radial build for reduced size machine
and new winding pack dimensions (ORNL).
Recalculate performance parameters (Reiersen).
Update assessment of NB access at reduced
(0.82) size (Cole). Is beam scraping required? Is there a 21 coil solution or do we need to
go to 18 coils?
Provide assessment of Brown’s alternate design
concept (Nelson).
The telecons have been running TOO LONG. If you could provide requested info via e-mail in advance of the
meeting, we could cut down on the material that we really need to go over. In addition, I will post an agenda prior to
the telecon with scheduled time slots.
Those folks who are interested in only a subset of the items on the
agenda could plan on attending only part of the meeting. Thank you for your continued patience and
hard work!