NCSX Memorandum
To: T. Brown, A. Brooks, H-M. Fan, B. Nelson, D. Williamson, M.
Cole, P. Goranson, R. Hatcher, C. Neumeyer, L. Dudek, P. Heitzenroeder, R.
Ramakrishnan, J. Chrzanowski, L. Dudek, A. Klink, H. Kugel
CC: J. Schmidt, H. Neilson, J. Lyon, S. Hirshman, M. Zarnstorff,
A. Reiman. L. Berry, D. Strickler, R. Simmons
From: W. Reiersen
Date: 1/26/2001
Re: Minutes of 1/24 Engineering telecon
An
engineering telecon was held on January 17.
The purpose of the meeting was to review the scope and cost associated
with machine assembly. Chrzanowski had
a nice presentation summarizing the above. A number of issues and action items arose
during discussions and are summarized below.
1.
Chrzanowski
included drafting support for the layout of the test cell. This was also included under Design
Integration in WBS 8. (Reiersen to
resolve)
2.
It
was not clear what the industrial contractor responsible for the modular / TF
coil assembly would be delivering.
Would the contractor be delivering parts (21 radial plate/TF coil
assemblies and 21 modular coil assemblies) that had been fit up, match drilled,
tested, and accepted at the contractor’s facility or will we be doing this for
the first time in the TFTR test cell?
If the assemblies are pre-fit at the contractor’s facility, how many
pieces do we need to break the completed assembly into for shipping? What testing will be required prior to
acceptance? This decision would appear to affect where the costs appear more so
than the bottom line since the activities will have to be done one place or the
other. Nelson indicated that he might
have some pre-assembly costs in WBS 1.
Perhaps these costs should all be tallied in WBS 72. (Nelson and Chrzanowski to resolve)
3.
The
subject of welding port extensions was discussed. Manual welding from inside the vacuum vessel appears difficult
due to space limitations. Using an
orbital welder on circular ports of a few standard sizes appears to be an
attractive direction to go. For
odd-shaped ports, a bolted connection for the port extensions might be easier
to accommodate. (Nelson to
address)
4.
The subject of whether the field assembly of the vacuum vessel
would require bolted or welded joints was discussed. Bolted joints offered many advantages but would require space
that might not be available. (Nelson to
resolve)
Trim coils were discussed during the course of the
meeting. The concepts
proposed by Brooks looked more attractive than previous incarnations. Concept development will continue.
Next week will be the NCSX project meeting. There will be no engineering telecon. The next engineering telecon is scheduled
for February 7.