By:
James H. Chrzanowski |
|
January 24, 2001 |
|
|
|
|
|
|
|
WBS 710
“Planning and Oversight” |
|
WBS 720 “On
Site Pre-Assembly Activities” |
|
WBS 730 “Test
Cell & Basement Assembly Activities” |
|
WBS 740 “Measurement
Systems” |
|
|
|
|
|
|
|
|
|
|
|
WBS 710 “Planning
and Oversight” |
|
Includes costs associated with planning and
overseeing the assembly of the Vacuum Vessel /Coil Field Periods, plus the
final assembly of the NCSX machine in the C-site Test Cell. |
|
Responsible for coordinating all NCSX Test Cell
activities including those Pre-assembly activities in the TFTR Test Cell |
|
|
|
|
|
|
|
|
WBS 710 “Planning
and Oversight” |
|
Developing plan for assembly of machine
components |
|
Integration between WBS elements involving
assembly issues |
|
Initiating and maintaining General Arrangement
Drawing of Test Cell |
|
Designing tooling required for component
assembly |
|
Design and fabrication of machine platform |
|
|
|
|
|
|
|
|
Tooling Design and Material Procurements |
|
Special assembly and lifting fixtures and
tooling |
|
$100.0 k ~ $125.0 k (w/25% G&A) |
|
General procurements ( miscellaneous items
required for assembly- safety, tools, disposable items, etc.) |
|
$ 20.0 k ~ $ $25.0 k (w/25% G&A) |
|
Platform Materials |
|
$35.0 k ~ $ 44.0 k (w/25% G&A) |
|
|
|
|
|
Labor Requirements: |
|
Construction Manager (1726 mhrs) |
|
Engineering support (2857 mhrs) |
|
Construction Safety Representative ( 1726 mhrs) |
|
Industrial Hygiene (863 mhrs) |
|
Quality Control (863 mhrs) |
|
Cadd Designer
(1295 mhrs) |
|
Technician/ Monthly Support: (2386 mhrs) |
|
Material & Supplies: $155.0 k ~ $194.0 k (w
G&A) |
|
Estimated Cost: $1,360 k |
|
|
|
|
|
WBS 720 “On
Site Pre-Assembly Activities” |
|
This WBS section includes the costs associated
with the receipt, assembly, alignment and vacuum leak testing of the (3)
field periods |
|
|
|
|
|
|
|
WBS 720 “On
Site Pre-Assembly Activities” |
|
The assembly of the VV/Coil Modules will occur
in the abandoned TFTR Test Cell located at D-site |
|
Area Preparation: $57.6 k (720 mhrs technician
and monthly support) |
|
Sufficient floor space and crane capacity
available (110 Ton capacity) |
|
Manpower dependent- Multiple segments could be assembled simultaneously |
|
|
|
|
|
|
|
Assumptions |
|
The vacuum vessel will be delivered to the TFTR
Test Cell in three sections |
|
The TF coils and Modular coils will be delivered to the TFTR Test Cell as
separate components |
|
|
|
|
|
|
TF Coil Systems |
|
Receive, inspect and test TF and Modular coils |
|
$23.1 k (288
mhrs Tech. & Monthly Support) |
|
Assemble all of the TF/Modular coils together
for fit up and alignment |
|
Components may have to be match reamed |
|
Alignment equipment will be required (laser or
“Faro” measuring arm required) |
|
$147.2 k (1840 mhrs) approx. 2.5 months |
|
|
|
|
|
|
|
Assemble Field Period Components |
|
Assemble each of the three Field Periods |
|
TF coils/Modular coils/vacuum vessel and Trim
coils |
|
Slide TF/ Module coil assemblies onto the vacuum
vessel and align/fasten coil structures together |
|
Hang Vacuum vessel from Coil support structure |
|
MIG weld port extensions to the vacuum vessel |
|
(22) extensions per field period |
|
|
|
|
|
|
|
|
|
|
|
Assemble Field Period Components-continued |
|
Vacuum leak Field Period segment |
|
Install Trim coils inside of the vacuum vessel |
|
PFC’s to be installed after final assembly of
all three periods in the NCSX Test Cell (welded scenario) |
|
Transport “Field Period” to the NCSX Test Cell |
|
Cost per field period assembly $ 167.7 k |
|
Approximately 16 weeks per assembly |
|
|
|
|
|
|
|
|
WBS 73 “Test Cell & Basement Assembly” |
|
This WBS section includes the assembly of all
the NCSX Torus components in the Test Cell including: |
|
All support structure |
|
Vacuum vessel & coil systems |
|
Cryostat |
|
Test Cell Platform (inc. lighting, fire
detection, suppression system under platform) |
|
|
|
|
Machine components will be assembled in the
PLT/PBX Test Cell |
|
25 Ton Overhead Crane will be used to assemble
components |
|
|
|
|
|
|
|
|
|
Activities not included in this WBS : |
|
Bus runs to the coils (WBS 400) |
|
Cryo-line connections (WBS 600) |
|
Bakeout system installation & connections (WBS 600) |
|
Water system connections (WBS 600) |
|
Neutral Beam Installations (WBS 200) |
|
External Diagnostic Installations (WBS 300) |
|
Shield wall modification & installation (WBS
600) |
|
Vacuum pump system (WBS 200) |
|
External Diagnostics (WBS 300) |
|
|
|
|
|
|
|
|
Activities not included in this WBS : |
|
GPP Activities |
|
Lighting Upgrade |
|
Test Cell Roof upgrade ?? |
|
Dew Point Control needs repair |
|
C-site Cooling Tower Upgrade |
|
Upgrade Central Chilled Water Plant |
|
|
|
|
|
|
Machine Assembly Sequence |
|
Install/align machine support columns |
|
Install lower support rings |
|
Install lower cryostat floor |
|
Position lower PF-3 & 4 coils in support
Rings |
|
Pump down & Leak Check Vacuum Vessel |
|
|
|
|
|
|
|
|
|
Install 1st. Field Period |
|
Install 2nd. Field Period |
|
Install 3rd. Field Period |
|
|
|
|
|
|
|
|
|
Install Vacuum pump system |
|
(WBS 200) |
|
Pump down & Leak check Vacuum vessel |
|
Complete installation Bakeout connections (WBS
600) |
|
|
|
|
|
|
Raise into position Lower PF 3 & 4 |
|
Install Upper PF-3 & 4 |
|
Install PF-1 & 2 Solenoid |
|
|
|
|
|
|
Machine Assembly Sequence- continued |
|
Installation of PFC’s and Internal Diagnostics |
|
Weld support hardware and plumbing |
|
Approximately 2 months x 3 men |
|
Assemble tile subassemblies (outside VV) |
|
Approximately 2 months x 2 men |
|
Install Internal PFC’s & Diagnostics |
|
Approximately 4 months x 4 men |
|
Estimated Cost $300.0k |
|
|
|
|
|
|
|
Machine Assembly Sequence- continued |
|
Install Bus connections to coil systems (WBS
400) |
|
Connect Cryostat and water lines (WBS 600) |
|
Install Platform around machine |
|
Install external diagnostics (WBS 300) |
|
|
|
|
|
|
|
Install Cryostat walls and ceiling |
|
Install collars and boots around feedthru’s |
|
|
|
|
|
|
|
Estimated cost excluding WBS 740 |
|
$ 2,875 .0 k |
|
|
|
|
|
|
Rates Used For Estimating |
|
Engineering -mechanical & electrical (EM) |
|
$130.00 per hour |
|
Senior lab (SM)/Technicians (TB) and Cad Designers(DM) |
|
$80.00 per hour |
|
Material & Supplies |
|
Cost plus 25% G&A |
|
No contingency included in estimates |
|