J.H. Chrzanowski
9
WBS 700 Machine Assembly
•WBS 720  “On Site Pre-Assembly Activities”
–The assembly of the VV/Coil Modules will occur in the abandoned TFTR Test Cell located at D-site
•Area Preparation: $57.6 k (720 mhrs technician and  monthly support)
–Sufficient floor space and crane capacity available (110 Ton capacity)
–Manpower dependent-  Multiple segments could be assembled simultaneously
•