J.H. Chrzanowski
13
WBS 700 Machine Assembly
•Assemble Field Period Components-continued
–Vacuum leak Field Period segment
–Install Trim coils inside of the vacuum vessel
–PFC’s to be installed after final assembly of all three periods in the NCSX Test Cell (welded scenario)
–Transport “Field Period” to the NCSX Test Cell
–Cost per field period assembly  $ 167.7 k
–Approximately 16 weeks per assembly
•