•Assemble Field Period Components-continued
–Vacuum leak Field
Period segment
–Install Trim coils inside of the
vacuum vessel
–PFC’s to be installed after final
assembly of all three periods in the NCSX Test Cell (welded scenario)
–Transport “Field Period” to the NCSX
Test Cell
–Cost per field period assembly $ 167.7 k
–Approximately 16 weeks per assembly
•