–Activities not included
in this WBS :
•Bus runs to the
coils (WBS 400)
•Cryo-line
connections (WBS 600)
•Bakeout system
installation & connections (WBS
600)
•Water system
connections (WBS 600)
•Neutral Beam
Installations (WBS 200)
•External
Diagnostic Installations (WBS
300)
•Shield wall
modification & installation (WBS 600)
•Vacuum pump system (WBS 200)
•External
Diagnostics (WBS 300)
•