WBS 700 Machine Assembly
•Machine Assembly Sequence- continued
–Installation of PFC’s and Internal Diagnostics
–Weld support hardware and plumbing
•Approximately 2 months x 3 men
–Assemble tile subassemblies (outside VV)
•Approximately 2 months x 2 men
–Install Internal PFC’s & Diagnostics
•Approximately 4 months x 4 men
•Estimated Cost $300.0k
–