•Machine Assembly Sequence- continued
–Installation
of PFC’s and Internal Diagnostics
–Weld
support hardware and plumbing
•Approximately 2 months x 3 men
–Assemble
tile subassemblies (outside VV)
•Approximately 2 months x 2 men
–Install
Internal PFC’s & Diagnostics
•Approximately 4 months x 4 men
•Estimated Cost $300.0k
–