October 25, 2001
Coordination Meeting - Central I&C Systems (WBS 5)
A coordination meeting was held on October 25 with Gary Oliaro, Bob Simmons, and Wayne Reiersen. Three topics were discussed:
WBS | |
Scope of work for CDR | |
Work plans and resource requirements |
Reiersen provided a revised WBS Dictionary. The elements remained the same. The descriptions were modified slightly. The revised WBS also reflects the new guidance that everything required through the Initial Ohmic Phase of operations (Phase 3) should be part of the construction project. The revised WBS Dictionary for WBS 5 is posted here.
The following agreements were made:
The work plan for WBS 5 leading up to the CDR consists of the following steps:
Current resource allocations for this task are:
Oliaro (13 days) |
All work against this job should be charged to 1808-NCSX-5X01.