October 30, 2001
Coordination Meeting - Site and Facilities (WBS 6)
A coordination meeting was held on October 25 with
Larry Dudek, Bob Simmons, Jerry levine, Jim Chrzanowski, Phil Heitzenroeder, and Wayne Reiersen. Three topics were
discussed:
| WBS |
| Scope of work for CDR |
| Work plans and resource requirements |
Reiersen provided a revised WBS
Dictionary. The revised WBS also reflects the new
guidance that everything required through the Initial Ohmic
Phase of operations (Phase 3) should be part of the construction project.
Also, everything required for the installation and testing of the two neutral
beams (e.g., water cooling) should also be part of the construction
project. The revised WBS
Dictionary for WBS 6 (including revisions made as part of the coordination
meeting) is posted here.
The following positions/action items were
adopted:
- The vacuum manifold around the device
should be moved to Vacuum Pumping Systems (WBS 22) pending concurrence from
Henry Kugel. [Kugel]
- Tom Brown (WBS 82) should expedite
development of a general arrangement drawing for the test cell and
basement. The drawing would show where the pits are located, the
shield walls, the entrances to the Test Cell, and the basement layout.
There was strong sentiment for placing the device in the center of the NCSX
Test Cell to maximize space around the device. [Brown]
- Seismic and shielding requirements need to
be developed for the shield blocks. [Reiersen]
- The vacuum pumping system might have to be
exhausted to the outside world. Monitoring did not appear necessary
but this should be confirmed. [Kugel]
- Responsibility for clearing the TFTR racks
from the PLT/PBX Test Cell needs to be assigned and scheduled. [Chrzanowski]
- Chrzanowski will update the description of
WBS 621 - Test Cell Cleanup to reflect tasks undertaken and completed by
other organizations, e.g. removal of the lead in the Test Cell by ER/WM. [Chrzanowski]
- WBS 62 was changed to C-Site (CS) Water
Cooling System Modifications. The NCSX project, as its only user, will
take ownership of the CS Water Cooling System and be responsible for the
modifications required. The interface to the C-site infrastructure
will be at the chillers, pending concurrence by JW Anderson. [Dudek]
- Vacuum Vessel & PFC Heating and Cooling
(WBS 625) was moved out of WBS 62 and renumbered as WBS 65.
- The NCSX Project needs to document what it
is relying on the ES&H and Infrastructure Support Department to
provide. Specific items include fire suppression in the test cell,
test cell ventilation and dew point control (HVAC), roofing over
experimental areas, and leak-proof walls. [Reiersen]
Work plans for WBS 6 leading up to the CDR
should should be drafted and include the following:
- Identify space requirements for each
WBS. Identify all site prep work. (Chrzanowski, 12/21)
- Develop shielding and seismic requirements for test
cell walls (Reiersen, 12/21)
- Identify heating and cooling requirements
for each WBS (Dudek, 12/21)
- Determine work required to re-commission
the C-Site helium supply system to deliver helium to the two neutral beams in
the Test Cell (Dudek, 1/15)
- Update the Conceptual Design of WBS 6 (Dudek,
2/15)
- Develop cost and schedule inputs for Bob
Simmons (Dudek, 3/1)
- Develop system description for inclusion in
CDR documentation (Dudek,
3/15)
- Prepare presentation for CDR (Dudek,
3/31)
Current resource allocations for this task
are:
| Dudek (4 weeks) |
| Gettelfinger (3 weeks) |
| Chrzanowski (9 weeks, but is mostly for WBS
7) |
Work plans should be drafted and resource
requirements identified (Dudek, 11/9).
All work against this job should be charged to
1808-NCSX-6X01.