SIT Meeting
June 24, 2002
Engineering Issues (Reiersen)
- WBS/Organizational
Issues – An organizational chart for the Engineering organization has been
developed, consistent with the proposed WBS. There are still a couple of loose ends dangling.
- Magnetic
Diagnostics – Magnetic diagnostics have been moved to WBS 1. However, our rationale for making that
change might have been flawed.
Lazarus (ORNL) will be responsible for defining magnetic
diagnostic requirements. In that
capacity, he will report through Mike Z (Project Physics). Designing the magnetic diagnostics is
a bit of an art, requiring previous experience in successfully avoiding
problems such as RF coupling.
Nobody with substantial, relevant experience has been identified
at ORNL. PPPL has several likely
candidates, presently engaged in NSTX.
GA and presumably MIT also would have qualified candidates. If the magnetic diagnostics are
designed at PPPL, it makes sense to build them here also. The Project needs to consider
moving magnetic diagnostics back under WBS 3.
- Integrated
Systems Testing – Hawryluk suggested that Integrated Systems Testing
would likely be performed by the Operations Group prior to first plasma,
not the Construction Group. This
would argue for moving Integrated Systems Testing back under WBS 9.
- FY02
Planning – Planning for FY02 is lagging.
A status is provided below.
Our target date is to have plans and resource requirements for
FY02 in place by the next SIT meeting on July 1.
- WBS
1 – Drafting of plans is largely complete. These plans need to be reviewed with cognizant engineers.
- WBS
2 – A kick-off meeting was held with Tim Stevenson and Bill Blanchard on
Friday, June 21 (minutes to be posted).
Tim will be taking over NBI (WBS 25) from Kugel. Blanchard will be taking over WBS
21-23. Plans for WBS 2 were
discussed. Their priorities will
be to review the scopes of work in their respective WBS elements, review
the cost and baselines, ensure that the legacy equipment on PBX is
properly tagged and stored, and submit Job Estimate Proposals for FY03
work prior to FY03.
- WBS
3 – The priority should be to support the development of the stellarator
core with regard to diagnostic interfaces. No metrics have been set yet.
- WBS
4 – Work scope has been discussed with Raki. Need to finalize deliverables and resource requirements.
- WBS
5 – Development of FY03 work plans is the only foreseen task.
- WBS
6 – Work plans drafted. Need to
be reviewed with cognizant WBS managers and have resource requirements
finalized.
- WBS
7 – Nothing has been done here.
- WBS
8 – Substantial amount of work needs to be accomplished between now and
October 1. Schedules and resource
requirements need to be established.
- Meetings
– SIT meetings are held weekly. (I would like to invite Dudek and Perry,
starting as soon as they can make it but not later than October.) Ditto for WBS 1 Integration meetings
(ORNL/PPPL telecon). We will meet
once a month with cognizant WBS Managers for a cost and schedule
review. Blanchard strongly
suggested a bi-weekly integration meeting with WBS Managers. Since WBS 1 already has a weekly
integration meeting at which many of these issues could be raised, I am
inclined to hold a project-wide integration meeting (telecon) perhaps once
a month to bring everyone up to speed on what is going on elsewhere in the
Project and provide a forum for folks to discuss issues of concern. Maybe we could pre-empt the WBS 1
integration meeting for a project-wide integration meeting once in a while
rather than scheduling yet another meeting.
- CDR
Recommendations – Comments requested by June 28.