From: Hutch Neilson [hneilson@pppl.gov]
Sent: Wednesday,
October 30, 2002 1:10 PM
To: bsimmons@pppl.gov; wreiersen@pppl.gov;
Warren.Marton@science.doe.gov; gpitonak@pppl.gov
Subject: Items for
next NCSX IPT meeting 11/5
The agenda items I see for next week are:
(1) DOE Update -
Pitonak, Marton
(AEP, CD-1, EIR expectations, misc. news of
interest)
(2) Project status and recent accomplishments
Overview- Neilson
Coil geometry- Neilson
Engineering issues and procurements- Reiersen
(3) CD-2 deliverables: status, plans.
1. Final Project Execution plan
2. Detailed cost & schedule baselines (based on resource loaded
schedules)
3. Complete preliminary design documents for major
subsystems
4. Preliminary Design Review (PDR) & report
5. Independent Project Review (IPR) & report
6. Technology development (R&D) results and decisions for
procurement
7. Revised risk assessment and mitigation plans
8. Final EA/FONSI
9. Systems Engineering Management Plan
10. Integrated Systems Test Plan
Greg should address 5 & 8; project will address the others.
Anything else? Bob will soon announce the arrangements for the
meeting.