From: Hutch Neilson [hneilson@pppl.gov]
Sent: Wednesday,
November 20, 2002 9:07 AM
To: wreiersen@mailserver.pppl.gov;
mzarnstorff@pppl.gov; bsimmons@mailserver.pppl.gov; Brad Nelson;
rstrykowsky@mailserver.pppl.gov; lyonjf@ornl.gov; John A. Schmidt
Cc:
hneilson@mailserver.pppl.gov
Subject: REVISED Summary of NCSX SIT
Meeting of 11/19/02
REVISED Summary of NCSX SIT Meeting of Tuesday, Nov. 19, 2002
Revised to correct typo's and expand on the re-baselining discussion in
1.e. to address the CR impacts.
1. FY-03 Work Planning and Authorization (Ron)
Ron issued a cost and schedule performance report based on the first
month's status reporting. Some concerns raised by this report were
discussed:
a. There is a large peak in the planned spending profile in Jan-Mar,
followed by a sharp drop-off. The effect is particularly pronounced at ORNL, and
is viewed as unrealistic. ACTION: Ron work with Brad to identify ways to smooth
the resource profile.
b. Spending at ORNL was well below plan in October. What are the
implications? ACTION: Brad.
c. Who is procuring the conductor for the prototype windings? I do not see
it in the WAFs. ACTION: Ron.
d. Do the WAFs adequately reflect the plan, in terms of logic and
deliverables? The consensus is that the WAFs provide an adequate basis for
authorization of the near-term FY03 work, but there is room for further
improvement. Improvements should be pursued as part of monthly statusing
meetings until the WAFs are deemed good enough. ACTION: Wayne, on an
ongoing basis, identify where improvements are needed and direct affected WBS
managers accordingly.
e. Have we established an initial baseline? Or will the PDR baseline
be the initial baseline? Will an ECP be needed to move to the PDR
baseline?
Discussion: The project needs to be working off a baseline. The CDR design
is our technical baseline. We should double check to make sure that we have
documented it as we stated in our CMP (e.g., stored the CAD model and
accompanying specs, i.e. the GRD). ACTION: Bob.
The C&S baseline is the $73.5M/June-07 plan as documented in the PEP.
The WAFs, our performance measurement baseline, were derived from the baseline
schedule though some modest inconsistencies have opened up. They can be
reconciled when we re-baseline for the PDR. We have not yet documented the
project-level milestones which are needed to provide adequate control. ACTION:
Ron, with help from John.
In summary: we have a baseline but we may need to complete the
documentation. We will need to re-baseline sometime before the PDR to capture
technical changes, recognize cost and schedule impacts that we know about, and
do a reset to account for the change in project schedule brought about by the
continuing resolution. It may require an ECP; Bob is reported to be compiling a
list of the changes.
2. Critical Issues (Wayne)
Critical issues were documented in a Nov. 8 memo by Wayne. A status update
issued on Nov. 18 showed progress in resolving the issues. Solutions have been
proposed but in most cases require confirmation via design studies or R&D.
Diagnostic port integration is highlighted as an area in need of
attention.
3. Next IPT Meeting with DOE: Tues., Dec. 17 at 11:00.
Agenda topics will include a discussion of what Bob has learned about the
EIR and its relationship to the PVR, and an update on CD-2 items.
4. Next NCSX PAC Meeting: Dec. 9-10.
Updated planning document was issued. Dry runs are tentatively planned for
Dec. 3.
5. Next SIT Meetings: Monday, Nov. 25 at 11:00 a.m. EST.
Summary by:
Hutch Neilson